A N N UA L R E P O R T
Auric Mining Limited and Controlled Entities
ABN 29 635 470 843
OVERVIEW 03
Letter from the Chair 04
Letter from the Managing Director 06
Overview of Mining Activities 09
Mineral Resources and Reserves 20
Mineral Resources and Ore Reserves Governance Statement 22
Competent Persons Statements 23
Schedule of Tenements 25
REVIEW OF ACTIVITIES 08
ADDITIONAL ASX INFORMATION 82
CORPORATE DIRECTORY 86
Contents
FINANCIAL REPORT 28
Directors’ Report 29
Remuneration Report (Audited) 39
Auditor’s Independence Declaration 46
Consolidated Statement of Profit or Loss and 47
Other Comprehensive Income
Consolidated Statement of Financial Position 48
Consolidated Statement of Changes in Equity 49
Consolidated Statement of Cash Flows 50
Notes to the Consolidated Financial Statements 51
Consolidated entity disclosure statement 74
Directors’ Declaration 75
Independent Auditors’ Report 76
Corporate Governance Statement 81
AURIC MINING | ANNUAL REPORT 2025
2
OVERVIEW REVIEW OF ACTIVITIES FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
OVERVIEW
AURIC MINING | ANNUAL REPORT 2025
3
REVIEW OF ACTIVITIES FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
OVERVIEW
Letter from
the Chair
Steven Morris
Dear Fellow Shareholders,
2025 was the year Auric Mining came of age as a gold
producer in our own right. Having spent several years
building the foundations by acquiring the right projects,
attracting the right team, and proving our strategy
through the highly successful Jeffreys Find joint
venture — we entered 2025 with the momentum and
conviction to take on mining in our own right. All of this
was against the backdrop of a favourable gold price.
The results were fantastic and, we are happy to
report, saw us face the end of 2025 with as much
optimism for 2026.
Our flagship asset, the Munda Gold Mine, came to
life this year. The Starter Pit was developed, ore
was mined, hauled, and processed through the
Lakewood Mill, and the first gold pour from our own
operations was completed in October 2025. The
financial contribution from Munda’s first campaign
of A$10.8 million net cash to Auric, against planning
estimates that were considerably more conservative,
is a pure statement of the quality of the orebody and
the operational capability of the team Mark English
has assembled.
Against this backdrop, the Company delivered its third
consecutive year of profitability. Revenue grew 144%
to $20.6 million, net profit after tax rose 92% to $5.2
million, and total assets grew 61% to $34.8 million.
Free cash flow of $6.5 million — up 129% on the prior
year — puts Auric in a position of financial strength as
we head into 2026 and the receipt of revenue from
the second stage of the Starter Pit.
The acquisition of the Burbanks Gold Processing
Plant, finalised on 30 September 2025, is another
milestone of which the Board is particularly proud. For
$4.4 million, a compelling discount to replacement
value, we secured a fully permitted, 180,000 tonnes
per annum CIL processing facility 10 kilometres south
of Coolgardie. Burbanks fundamentally changes our
strategic position. Rather than relying on third-party
toll millers, Auric is now on a pathway to becoming a
vertically integrated gold producer with control over
its own processing destiny.
We also made meaningful progress on the Lindsay’s
Gold Project acquisition, completing settlement on
four tenements in November 2025, and assumed
management of the Wardens Court proceedings
relating to M27/169. The Loded Dog tenement
package in the Higginsville area was fully acquired
during the year, adding eight prospective tenements
to our portfolio.
Your Board has continued to strengthen its
oversight of risk, operational performance, and
capital allocation. We are acutely aware of the
responsibilities that come with an accelerating
operational profile, and we are committed to the high
standards of safety, environmental stewardship, and
transparency that our shareholders and the broader
community rightly expect. I am pleased to report that
there were no lost time injuries, medically treated
injuries, or alternate duty injuries recorded across our
operations during the year.
AURIC MINING | ANNUAL REPORT 2025
4
REVIEW OF ACTIVITIES FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
OVERVIEW
I want to acknowledge the fantastic efforts of
Mark English, John Utley, Catherine Yeo and the
entire Auric team from the mine site at Munda
to the offices in Perth. Maintaining strategic and
operational discipline across a growing organisation
now mining in its own right is critical to long term
growth and profitability.
As we look to 2026, the second processing
campaign for the Munda Starter Pit is already
underway, and planning for the much larger Munda
Main Pit has commenced. Engineering studies
at Burbanks are advancing, and we are actively
progressing the Lindsay’s acquisition. The gold price
environment remains highly supportive.
The Board is confident that the foundations laid in
2025 and indeed from inception position us for a
significant step-change in scale and value creation in
the years ahead. On behalf of the Board, I would like to
thank you for your continued support.
Yours sincerely,
Steve Morris
Non-Executive Chair
AURIC MINING | ANNUAL REPORT 2025
5
REVIEW OF ACTIVITIES FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
OVERVIEW
Letter from the
Managing Director
Mark English
Dear Shareholders,
This year, without question, was the most significant
year in Auric’s short history. It was the year we stopped
watching the gold industry and joined it — on our own
terms, with our own equipment, our own people, and
mining in our own right.
For the third consecutive year, Auric has delivered
an excellent result. Net profit after tax of $5.2 million
represents a 92% increase compared to last year , and
our revenue of $20.6 million — up 144% — reflects the
tangible output of a Company that is now genuinely
producing gold. These results are the product of
disciplined operational execution and a team that has
delivered at every stage.
Jeffreys Find – A Fitting Conclusion
The Jeffreys Find Gold Mine Joint Venture with
BML Ventures Pty Ltd concluded its eighth and final
processing campaign in August 2025, marking the end
of a remarkable chapter for the Company. Over the life
of the project, 29,537 ounces of gold were produced
from a two-stage open-pit operation that generated
A$112 million in total gold sales at an average realised
price of A$3,792 per ounce. Auric’s cumulative cash
generated from the joint venture totalled approximately
$14.5 million as at 31 December 2025 — a phenomenal
return on a modest capital investment of approximately
$1.2 million for acquisition and development, prior to
mining. The project demonstrated that disciplined
acquisition and sound geological judgement can
generate outstanding returns for shareholders,
even from smallish deposits. Site rehabilitation was
completed during the December quarter.
Munda – Auric Mining in our own Right
The Munda Gold Mine was the centrepiece of 2025.
Mining of the Starter Pit commenced in May 2025,
and by year-end, approximately 406,000 Bank Cubic
Metres of ore had been mined, with the pit floor at
approximately 45 metres below surface. Our team —
employed directly by Auric and utilising a dry-hire fleet
from MHM Contracting — delivered a safe, efficient
operation from day one.
The first processing campaign at Black Cat Syndicate’s
Lakewood Mill in Kalgoorlie commenced on 12 October
2025 and was completed ahead of schedule on 2
November 2025. The results were outstanding:
57,900 dry tonnes milled at a reconciled head grade
of 1.61 g/t Au with a mill recovery of 90.67% — better
than our pre-feasibility assumptions on both grade
and recovery. The 2,718 ounces of gold produced
generated A$16.85 million in gross revenue and
A$10.82 million in net cash to Auric after all milling,
haulage, and royalty costs. At an average realised price
of A$6,200 per ounce, the gold price environment was
excellent.
At the close of the year, approximately 67,000 tonnes
of high-grade ore was stockpiled at Munda ready for
the second campaign, scheduled to commence at
Lakewood in late January 2026. Mining of the Starter
Pit concluded in January 2026. Reconciliation of
Campaign One results with resource and grade control
models will inform the detailed design of the much
larger Munda Main Pit, with permitting applications for
the main pit targeted for late 2026.
AURIC MINING | ANNUAL REPORT 2025
6
REVIEW OF ACTIVITIES FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
OVERVIEW
Burbanks – Strategic Infrastructure Secured
The acquisition of the Burbanks Gold Processing Plant
on 30 September 2025 for $4.4 million was a defining
strategic move. The fully permitted and licensed,
180,000 tonne per annum CIL facility — located 10
kilometres south of Coolgardie with grid power, sealed
road access, and a water licence — is expected to
provide Auric with ultimately an in-house processing
solution for ore from Munda, Lindsay’s, and other nearby
projects. Metallurgical and engineering consultants
commenced desktop evaluation of expansion
options during Q4 2025. Owning our own processing
infrastructure is central to our strategy of becoming a
fully integrated gold producer and will materially improve
our control over production schedules and unit costs.
Lindsay’s and Loded Dog – Growing the Portfolio
On 19 November 2025, we executed the Tenement Sale
Agreement for the Lindsay’s Gold Project, completing
settlement on initially four tenements for $400,000. The
Project — which includes the Parrot Feathers open pit,
located 65 kilometres northeast of Kalgoorlie — adds
near-term open-pit mining potential to our portfolio.
We have assumed management of the Wardens Court
proceedings for M27/169 and remain committed to
completing the acquisition of the remaining tenements
upon successful resolution of the matters in the
Wardens Court.
We also completed the acquisition of all eight Loded
Dog tenements in the Higginsville area during the
June 2025 quarter. The package covers 113 km² and
includes the brownfields Amorphous and Foote’s Find
prospects. Drilling programs across Higginsville, Chalice
West, Spargoville, and Widgiemooltha Gold Project are
planned for the second quarter of 2026.
Financial Strength and Capital Discipline
Auric closed 2025 with $6.7 million in cash, no debt,
and an unhedged gold position — meaning we retain
full exposure to the gold price. Total equity grew 66%
to $29.7 million, and total assets reached $34.8 million.
During the June quarter, a $6.6 million placement was
completed to accelerate gold production and fund the
Burbanks acquisition. The Company entered into a $3.0
million loan facility with BML Ventures secured against
M15/87, of which $1.25 million was drawn and fully
repaid during the December quarter, there is no amount
outstanding at year-end.
Outlook
As I write, Munda’s second campaign has been
completed at Lakewood, and we are in active mine
planning for the Main Pit. Burbanks engineering studies
are progressing as well as recruitment of key personnel.
Lindsay’s acquisition is being advanced through the
Wardens Court. Exploration programs across the
portfolio are scheduled for April 2026. The gold price
remains at historically elevated levels.
The Auric team has delivered fantastic results to
date and is deeply committed to the Company and
our Shareholders. We have the assets, the team, and
the strategy and focus to build something of lasting
significance in Western Australian gold mining. I look
forward to reporting further progress throughout
2026. I thank all our Shareholders, old and new, for your
continuing support. I look forward to you welcoming you
at our Annual General Meeting on 28 May 2026.
Yours sincerely,
Mark English
Managing Director
AURIC MINING | ANNUAL REPORT 2025
7
REVIEW OF ACTIVITIES FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
OVERVIEW
REVIEW OF
ACTIVITIES
AURIC MINING | ANNUAL REPORT 2025
8
OVERVIEW FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
REVIEW OF ACTIVITIES
Overview of Mining Activities
Tenements
73
Covering Area
494
KM2
Projects
6
Auric Mining Limited (ASX:
AWJ) entered 2025 as
manager of 43 tenements
covering 360 km²
, with a
portfolio comprising four
projects:
1. THE WIDGIEMOOLTHA GOLD
PROJECT (INCLUDING THE
MUNDA GOLD DEPOSIT),
2.THE JEFFREYS FIND
GOLD MINE,
3.THE SPARGOVILLE PROJECT,
4.THE CHALICE WEST
PROJECT.
The year concluded with Auric
managing 73 tenements covering
494 km² across six projects — adding
the Burbanks Gold Processing Plant
and the Lindsay’s Gold Project as
formally defined project areas
— reflecting an active and highly
successful year of corporate and
operational development.
2025 was characterised by four major operational and strategic themes:
The successful completion of the Jeffreys Find Gold Mine Joint Venture, which concluded its
final processing campaign in August 2025 with total life-of-mine production of 29,537 ounces
and approximately $14.5 million in cumulative cash receipts to Auric by 31 December 2025;
The commencement and first processing campaign of the Munda Gold Mine — Auric’s first
owner-operated mine — with the first gold pour achieved in October 2025 and net cash of
A$10.82 million received from Campaign One;
The acquisition of the Burbanks Gold Processing Plant on 30 September 2025 for $4.4 million,
a transformational step toward vertical integration; and
Meaningful portfolio expansion through the Loded Dog tenement acquisition in Higginsville and
the commencement of the Lindsay’s Gold Project acquisition.
AURIC MINING | ANNUAL REPORT 2025
9
OVERVIEW FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
REVIEW OF ACTIVITIES
Key Financial Performance – Year Ended 31 December 2025
FY2025 FY2024 FY2023
Total Revenue $20,620,000 $8,450,000 $4,790,000
Net Profit After Tax $5,170,000 $2,690,000 $1,313,000
Current Assets $14,532,000 $10,287,000 $4,636,000
Total Assets $34,773,000 $21,621,000 $13,309,000
Total Equity $29,746,000 $17,937,000 $11,933,000
Free Cash Flow $6,504,000 $2,837,000 $2,492,000
Source: Auric Mining Limited Audited Financial Statements, year ended 31 December 2025.
For the third consecutive year, Auric delivered a profitable result. Revenue of $20.6 million (up 144% on FY2024)
and net profit after tax of $5.2 million (up 92%) reflect the Company's growing production profile. Total assets
grew 61% to $34.8 million and free cash flow increased 129% to $6.5 million. The Company held $6.7 million in cash
at year-end with no debt and an unhedged gold book.
Safety performance was exemplary throughout the year. There were no lost time injuries, no medically treated
injuries, and no alternate duty injuries recorded across any of Auric's operations during 2025.
Overview of Mining Activities (continued)
10 AURIC MINING | ANNUAL REPORT 2025
OVERVIEW FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
REVIEW OF ACTIVITIES
Figure 1. Auric’s projects in the Widgiemooltha-Norseman area.
Overview of Mining Activities (continued)
AURIC MINING | ANNUAL REPORT 2025
11
OVERVIEW FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
REVIEW OF ACTIVITIES
Widgiemooltha Gold Project
Munda Gold Mine
Background and Project Overview
The Munda Gold Mine is located approximately 5 kilometres from the township of Widgiemooltha in
the Eastern Goldfields of Western Australia, within Mining Lease M15/87. The deposit is included within
the Widgiemooltha Gold Project, which encompasses 37 tenements including five granted Mining
Leases within the Norseman – Wiluna greenstone belt — one of Western Australia's most productive
gold corridors.
The Munda gold deposit has been the subject of extensive exploration and resource definition work over
many decades, including drilling by Western Mining Corporation, Resolute Mining (which excavated a
small trial pit in 1999), and latterly Auric.
Auric drilled 55 deeper RC holes in 2021-22 and completed close-spaced 10m x 10m resource drilling
comprising 361 holes for 11,301m in early 2024. An updated Mineral Resource was declared in December
2024 (see Section 2.7), and a Pre-Feasibility Study, completed in December 2024, defined a Probable
Ore Reserve of 125,000t at 1.8 g/t for 6,100 contained ounces as the basis for the Starter Pit.
Mining Approvals and Site Preparation
During the March 2025 quarter, the Mining Proposal and Mine Closure Plan for the Munda Starter
Pit were approved by the Western Australian Government's Department of Energy, Mines, Industry
Regulation and Safety (DEMIRS). The Mining Operation Notification was acknowledged by the Mines
Inspectorate. A Native Vegetation Clearing Permit was also received.
Site preparation activities commenced in April 2025, including construction of a haul road, clearing
for ROM pads and waste rock landform footprint, establishment of a site office and laydown area, and
mobilisation of a mining fleet dry-hired from MHM Contracting Pty Ltd, the latter including a 125-tonne
excavator and four 40-tonne articulated Moxi dump trucks.
Figure 2. Munda Starter Pit.
AURIC MINING | ANNUAL REPORT 2025
12
OVERVIEW FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
REVIEW OF ACTIVITIES
Mining Operations – Starter Pit
Mining of the Munda Starter Pit commenced in May 2025 with Auric personnel supervising mining and grade
control and operating the mining equipment — a landmark transition for the Company from JV partner to mine
operator in its own right. Drill and Blast services together with grade control drilling were provided by Kalgoorlie-
based Total Drilling Services.
By the end of the December 2025 quarter, approximately 406,000 Bank Cubic Metres (BCM) of ore and waste had
been mined, with the pit floor at approximately 45 metres below ground surface. The first processing campaign
had been completed and ore stockpiles were building steadily in preparation for the second processing campaign.
Mining operations continued beyond the December quarter with further grade control and pit design refinements
allowing Auric to capture additional ore at the base of the pit. Mining of the Starter Pit was expected to conclude in
late January 2026.
At the close of 2025, approximately 71,000 tonnes of high-grade ore was stockpiled on the ROM pad at Munda,
ready for processing in Campaign Two at the Lakewood Mill.
Toll Milling – Campaign One
A Toll Milling and Ore Purchase Agreement was executed with Black Cat Syndicate Ltd (ASX: BC8) in July 2025,
providing for up to 125,000 tonnes of Munda Starter Pit ore to be processed at Black Cat’s Lakewood Mill in
Kalgoorlie. A Haulage Agreement was also executed with TLL Haulage Solutions Pty Ltd for transport of ore to
the mill.
Processing of the first parcel of approximately 57,900 tonnes commenced on 12 October 2025 and was
completed ahead of schedule on 2 November 2025. The first gold pour was achieved on 21 October 2025.
Campaign One final reconciliation was completed on 18 November 2025.
Figure 3. Munda gold pours at Lakewood Mill.
Widgiemooltha Gold Project – Munda Gold Mine (continued)
13 AURIC MINING | ANNUAL REPORT 2025
OVERVIEW FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
REVIEW OF ACTIVITIES
Campaign One – Final Production and Financial Results
Munda Campaign One – Final Production Metrics
Dry Tonnes Milled 57,900 t
Reconciled Head Grade 1.61 g/t Au
Mill Recovery 90.67%
Gold Recovered 2,718 oz
Average Sale Price A$6,200/oz
Total Gold Sales A$16,851,773
Less External Direct Costs (milling, haulage, royalties) (A$6,032,878)
Net Cash to Auric A$10,818,895
Grades were expected to increase with depth in the Starter Pit and the reserve grade estimate of 1.8g/t
represented the full Starter Pit. A reconciled head grade of 1.61g/t Au was therefore reasonable in that context.
Processing recovery of 90.67% (versus PFS assumption of 88% for oxide and transitional ore) was better than
pre‑mining testwork had suggested. The 2,718 ounces produced from 57,900 dry metric tonnes milled was sold at
an average realised price of A$6,200 per ounce — substantially above the PFS assumption of A$3,500/oz.
Campaign Two – Scheduled January 2026
An agreement for the second and final processing campaign for the Munda Starter Pit, comprising approximately
65,000 tonnes, was secured at Lakewood Mill with processing scheduled to commence in late January 2026.
The Company expected Campaign Two to build on the momentum established in Campaign One, with receipts
anticipated in early Q1 2026.
Widgiemooltha Gold Project – Munda Gold Mine (continued)
Figure 4. Munda gold doré bar.
AURIC MINING | ANNUAL REPORT 2025
14
OVERVIEW FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
REVIEW OF ACTIVITIES
Mine Infrastructure and WIN Metals Transaction
During the June 2025 quarter, Auric purchased the mining camp, permitted in-pit water supply at the former
132North nickel mine site, and all nickel rights at Munda from WIN Metals Limited for total consideration of
$1.4 million (ex-GST), payable in two tranches. The first tranche of $900,000 was paid on 30 June 2025 and the
second on 9 September 2025. This transaction gave Auric full operational control and ownership of all mineral
rights at Munda except lithium, which remains with WIN. The 20-man mining camp, located approximately
6 kilometres north of the Munda pit, provided essential accommodation infrastructure for the mining team
throughout operations.
On 30 April 2025, Estrella Resources Limited commenced legal action against a range of companies, including
Auric Mining Limited, for issues related to a lithium royalty associated with Munda and other tenements. Auric is
strongly defending the matter.
Munda Main Pit – Development Planning
The Starter Pit delivered critical operational, geological, and metallurgical data that will directly inform planning
for the larger Munda Main Pit. Reconciliation of grade control models with resource estimates, together with
geotechnical and metallurgical learnings from Campaign One, will form the basis of an updated resource estimate
and ultimately, pit optimisations and detailed mine design. Auric planned to commence this reconciliation and
planning process in Q1 2026, with the objective of applying for a Main Pit mining permit later in the year. The Main
Pit represents a significant opportunity to substantially increase gold output beyond Starter Pit levels and is
expected to form the core of Auric’s production profile for several years.
Widgiemooltha Gold Project – Munda Gold Mine (continued)
Figure 5. Munda camp site.
15 AURIC MINING | ANNUAL REPORT 2025
OVERVIEW FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
REVIEW OF ACTIVITIES
Burbanks Gold Processing Plant
The Burbanks Gold Processing Plant is located approximately 8 kilometres south of Coolgardie,
Western Australia. The facility is a fully permitted, 180,000 tonne per annum Carbon-in-Leach (CIL)
gold processing plant with established infrastructure including grid power, sealed road access, a water
licence, fully permitted site and Tailings Storage Facility. The plant was operational until approximately
June 2019, when the previous operator ceased activities.
Auric completed due diligence on the Burbanks facility during the March 2025 quarter and agreed to
acquire it for $4.4 million. Following resolution of various outstanding issues by the vendor (mortgagee in
possession), settlement was completed on 30 September 2025.
The Burbanks asset is held within 14 tenements including 3 granted Mining Leases and 5 General Purpose
Leases. The tenements are registered to BBL Milling, a wholly owned subsidiary of Auric Mining Limited.
Metallurgical and engineering consultants undertook an inspection of the plant during the December
2025 quarter and commenced a desktop-level assessment of several processing and development
options. The assessment will evaluate refurbishment requirements and operating costs for a 180,000
tonne per annum plant versus potential expansion of throughput capacity to between 500,000 and 1
million tonnes per annum The acquisition secures a long-term processing solution for ore from both the
Munda and Lindsay’s projects and underpins Auric’s strategy of becoming a vertically integrated gold
explorer, miner, and processor.
The acquisition price of $4.4 million represented a substantial discount to current replacement value,
and the Board regards the Burbanks asset as one of the most strategically significant additions to Auric’s
portfolio since its founding.
Figure 6. Burbanks Plant.
AURIC MINING | ANNUAL REPORT 2025
16
OVERVIEW FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
REVIEW OF ACTIVITIES
Jeffreys Find Gold Mine
The Jeffreys Find Gold Mine is located approximately 50 kilometres northeast of Norseman, Western Australia,
and comprises two tenements including one granted Mining Lease (M63/242) together with a third tenement
(E63/2535) applied for in the December quarter. The deposit was mined via a joint venture with BML Ventures Pty
Ltd of Kalgoorlie (BML), under which BML served as the miner, operator, and manager of the project, incurring and
paying all mining, haulage, milling, and related costs. Auric and BML shared surplus cash proceeds on a 50:50 basis
following deduction of all direct costs.
Stage 1 mining and processing was completed in 2023, yielding 9,741 ounces of gold sold at an average price of $3,006
per ounce and generating $4.76 million in cash to Auric. Stage 2 mining commenced in March 2024 and concluded
on 28 January 2025, with ore processed across eight campaigns at the Greenfields Mill and Three Mile Hill Plant near
Coolgardie. The eighth and final processing campaign was completed in August 2025 at Three Mile Hill.
Jeffreys Find Gold Mine Stage One 2023 Stage Two 2024–2025 Total Project to Dec 2025
Gold Recovered – Ounces 9,741 19,796 29,537
Average Sale Price per Ounce (AUD) $3,006 $4,134 $3,792
Cash to Auric $4.76M $9.1M $14.5M
As of 31 December 2025. Total figures are interim; subject to final reconciliation with BML Ventures in Q1 2026.
Total gold recovered over the life of the two-stage project was 29,537 ounces, generating A$112 million in gross
gold sales at an average realised price of A$3,792 per ounce. Auric’s cumulative cash receipts from the joint
venture totalled approximately $14.5 million at 31 December 2025, representing a highly successful return on an
initial investment of approximately $1.5 million.
Site rehabilitation at Jeffreys Find was undertaken by BML during the December 2025 quarter in accordance
with the project’s Mining Proposal and Mine Closure Plan. This included waste dump profiling, topsoil sheeting,
removal of all mining infrastructure, and ripping of cleared areas to enhance vegetation regrowth. Final project
reconciliation between Auric and BML was expected to be completed in Q1 2026.
The project conclusively demonstrated the merit of Auric’s joint venture model — a low-capital, zero-upfront-cost
structure that allowed Auric shareholders to benefit from the economics of a successful open pit gold mine.
Figure 7. Jeffreys Find Gold Mine.
17 AURIC MINING | ANNUAL REPORT 2025
OVERVIEW FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
REVIEW OF ACTIVITIES
Lindsay’s Gold Project
The Lindsay’s Gold Project is located approximately 65 kilometres northeast of Kalgoorlie, Western
Australia. The Project includes three pits, the largest of which is the Parrot Feathers open pit, from which
6,153 ounces of gold was produced in 2013 before operations ceased following a sharp fall in the gold
price. The area has a long mining history with first gold production recorded in 1897.
Auric executed a Binding Letter Agreement to acquire the Lindsay’s Project from Top Global Mining Pty
Ltd and NBC Mining Pty Ltd in February 2025. The total agreed purchase price is $4 million, comprising
$2 million in cash and $2 million in Auric shares, together with a royalty of 3.5% of Net Smelter Return
from gold produced. Due diligence was completed during the June 2025 quarter, with Auric confirming
satisfaction with results.
Settlement was staged due to Wardens Court proceedings affecting certain tenements:
● Four tenements not subject to Wardens Court proceedings were settled on 19 November 2025 for
$400,000, following execution of the Tenement Sale Agreement.
● Auric assumed sole management and responsibility for Wardens Court proceedings relating to M27/169,
with a further cash payment of A$1.3 million and issuance of A$2.0 million in Auric shares payable upon
successful resolution, together with a royalty of 3.5% of Net Smelter Return from gold produced.
● The vendors retain management of proceedings relating to M27/34 and M27/486, with contingent
payments of $50,000 and $250,000 respectively upon successful resolution.
At 31 December 2025, the Lindsay’s project comprised five tenements (L27/82, L27/84, E27/624,
E27/246 [pending], and P27/2406), with Auric retaining the right to purchase three further tenements
(M27/169, M27/34, M27/486) subject to resolution of the relevant Wardens Court matters.
The near-term potential for open-pit mining and toll treatment at Lindsay’s is a key strategic rationale.
Once fully acquired and permitted, the project would provide a second source of ore for toll milling
and, ultimately, for processing through the Burbanks plant. New tenement applications in the area
surrounding Lindsay’s were lodged during the year to extend Auric’s footprint.
Figure 8. The Parrot Feathers Gold Deposit Northeast of Kalgoorlie.
AURIC MINING | ANNUAL REPORT 2025
18
OVERVIEW FINANCIAL REPORT
ADDITIONAL ASX
INFORMATION CORPORATE DIRECTORY
REVIEW OF ACTIVITIES
Spargoville Project
The Spargoville Project is located approximately 30 kilometres north of Widgiemooltha, within the same
stratigraphy as the W