Gold from First Campaign of 2024 Delivered to Perth Mint
Released
Released
Announcement PDF
ASX Announcement
auricmining
7 May 2024
ASX: AWJ | ACN 635 470 843
30,300 Tonnes Processed in Opening Campaign of 2024.
Six Doré Bars Delivered to Perth Mint.
Highlights
•
30,300 tonnes processed by Coolgardie Mill for first gold campaign of 2024.
•
6 Doré bars weighing 64.68 kg delivered to Perth Mint.
•
First gold sales now imminent.
•
Total ounces and reconciliation of campaign to be advised.
•
Joint Venture remains on track to mill more than 300,000 tonnes in 2024.
Management Comment
Managing Director, Mark English, said “BML are wrapping up the first gold campaign
of the year from Jeffreys Find.
“It looks good and will create millions of dollars in gross revenue for our joint venture.
“BML are currently stockpiling ore at the mine and at the mill. The next processing
campaigns at the mill are scheduled for July and August 2024.
“Jeffreys Find Gold Mine will be a substantial cash producer to Auric throughout 2024
and 2025,” said Mr English.
Doré bars at Greenfields Mill.
page | 1
+61 8 9548 9997 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 7 May 2024
Auric Mining Limited (ACN 635 470 843)
Photo of the pit at Jeffreys Find (2 May 2024).
The Announcement
Through our joint venture with BML Ventures Pty Ltd of Kalgoorlie (BML), Auric Mining
Limited (ASX: AWJ) (Auric or the Company) is pleased to announce that toll milling
of 30,300 dry metric tonnes of gold ore from the Jeffreys Find Gold Mine (the Project)
near Norseman is now complete.
The Greenfields Mill at Coolgardie (Greenfields) commenced milling of Jeffreys Find
ore on 17 April 2024 and the campaign finished on 30 April 2024. The first six Doré
bars of the campaign, weighing 64.68kg, have been poured and dispatched to the
Perth Mint for refining and sale.
The number of ounces of gold from the campaign and gross revenue from gold
sales will be known shortly and advised to the ASX. BML are continuing to mine and
stockpile ore on the mine site ROM Pad and at the Greenfields Mill. The next gold
campaigns are scheduled for July and August 2024.
BML expects to mill more than 300,000 tonnes of ore during Stage Two of The Project.
Stage One saw 176,000 tonnes processed to recover 9,741 ounces of gold.
page | 2
+61 8 9548 9997 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 7 May 2024
Auric Mining Limited (ACN 635 470 843)
Doré bars at Greenfields Mill.
Forward Looking Statements
This Announcement may contain forward-looking statements which are identified
by words such as ‘may’, ‘could’, ‘should’, ‘believes’, ‘estimates’, ‘targets’,
‘expecting’, or ‘intends’ and other similar words that involve risks and uncertainties.
These statements are based on an assessment of present economic and operating
conditions, and on a number of assumptions regarding future events and actions
that, as at the date of this Announcement, are considered reasonable. Such
forward-looking statements are not a guarantee of future performance and involve
known and unknown risks, uncertainties, assumptions, and other important factors,
many of which are beyond the control of the Company, the Directors, and the
management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking
statements contained in this Announcement will actually occur and investors are
cautioned not to place undue reliance on these forward-looking statements.
This announcement has been approved for release by the Board.
Corporate Enquiries
Mark English
Managing Director
Auric Mining Limited
+61 409 372 775
menglish@auricmining.com.au
Follow our communications
Subscribe: auricmining.com.au
page | 3
+61 8 9548 9997 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
Share your feedback
Discover