Conditional Purchase of Lindsay's Gold Project
Released
Released
Announcement PDF
ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE
27 FEBRUARY 2025
Auric Executes Binding Agreement to
Purchase Lindsay’s Project
Highlights
•
Auric executes Binding Letter Agreement to purchase Lindsay’s Project from Top
Global Mining Pty Ltd and NBC Mining Pty Ltd, subject to Due Diligence.
•
Project comprises 8 tenements and includes the partially mined Parrot Feathers
gold deposit.
•
The 8 tenements encompass 33 square kilometres and include 3 granted Mining
Leases.
•
Potential for near term, open pit gold mining and toll treatment.
•
Total purchase price is $4 million, being a combination of cash and shares.
Management Comment
Mr Mark English, Managing Director said:
“The Lindsay’s Project fits within our strategy of acquiring near-term gold production
projects within trucking distance of mills in the Kalgoorlie area.
“This is an exciting opportunity to add to the gold ounces we control in the region.
It’s another big step in our growth toward sustained production.
“Due Diligence will be undertaken to confirm the total potential of the Lindsay’s
Project. The intention is to commence mining from the Parrot Feathers gold deposit
in 2025.
“Ore from the mine graded 1.93g/t Au and produced 6,153 ounces when last
mined. Mining was abandoned in 2013 because the gold price slumped, going
down to A$1,295 an ounce. Just 25% of the planned ore from an open pit was
extracted at that time. The project was never completed.
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE
27 FEBRUARY 2025
“The deposit is ripe for near-term mining and we are looking at re-directing our
mining team to Lindsay’s after completing the Munda Starter Pit. This would afford
us the opportunity to produce more ounces of gold whilst extensively planning a
broader main pit at Munda, which is our flagship asset.
“We thank Pasquale Princi, SEER Financial Group, and Chelsea Taylor, CTC
Geological, who acted as the corporate advisers to the vendors for their efforts in
reaching a mutually beneficial outcome for all parties.” said Mr English.
Photo. The Parrot Feathers Gold Deposit northeast of Kalgoorlie: December 2024.
The Announcement
Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to announce
that through a new wholly owned entity LMG (WA) Pty Ltd (LMG), Auric has
executed a Binding Letter Agreement to purchase the Lindsay’s Project, including
Parrot Feathers open pit gold mine from Top Global Mining Pty Ltd and NBC Mining
Pty Ltd (The Vendors) through its corporate advisers SEER Financial Group.
The Lindsay’s Project is located 50km northeast of Kalgoorlie, WA (Figure 1) and
comprises 8 tenements, including 3 mining leases, covering 33 km2. Open-pit mining
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE
27 FEBRUARY 2025
undertaken in 2013 ended abruptly with a sudden fall in the gold price and only
approximately 25% of the planned production was completed 1.
Figure 1. Top Global’s Lindsay’s Project and Auric’s projects north of Widgiemooltha.
1 (ASX: KGM) 18 October 2013. KalNorth Gold Mines Limited Annual Report to Shareholders 2013
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE
27 FEBRUARY 2025
The attraction for Auric is the near-term potential for open-pit mining and toll
treatment and thereby to produce gold and revenue.
The Company will pay The Vendors $100,000 by way of a non-refundable deposit in
consideration for which, Top Global has granted Auric the exclusive right to
complete Due Diligence on the project up till 3 April 2025.
Subject to successful completion of Due Diligence, at execution of the Tenement
Sale Agreement (TSA) Auric will:
•
Pay $2,000,0000 (plus GST in cash) to The Vendors, including the $100,000
deposit.
•
Issue shares to the value of $2,000,000 (plus GST in cash) to The Vendors,
calculated at the 15-day VWAP ending on the day prior to execution of the
TSA. The shares will be issued subject to shareholder approval at Auric’s
Annual General Meeting to be held prior to 31 May 2025. The Vendors have
agreed to enter into voluntary escrow as follows:
•
•
•
Shares to the value of $1,000,000 held in voluntary escrow for 6 months
from date of issue.
Shares to the value of $1,000,000 held in voluntary escrow for 12 months
from date of issue.
Grant The Vendors a royalty of 3.5% of the Net Smelter Return from the sale of
gold from the Lindsay’s Project.
The Lindsay’s Project
The area has a long mining history including first gold production in 1897, a mining
resurgence in the 1930’s and small-scale mining in the late 1980’s.
KalNorth Gold Mines Limited (KalNorth) commenced modern open pit mining at
Lindsay’s in January 2013 with ore processed at Saracen’s Carosue Dam mill, 70km
to the east of Lindsay’s. Mining ceased in August that same year following a drop in
gold price from a high of AUD$1,625 per ounce to as low as AUD$1,295 per ounce.
At that stage, KalNorth reported that 6,153oz gold was produced from 138,229t
grading 1.93g/t Au 2. Ore was mostly mined from the Parrot Feathers deposit with a
small tonnage (1,893t) extracted from the ‘Trial Pit’ (Figure 2).
In 2016, AIM-listed Keras Resources PLC submitted permit applications to
recommence mining at Lindsay’s based on both open pit and underground
mining 3. The permit applications were approved that year. One of the aims of Due
2 (ASX: KGM) 25 October 2013. Quarterly Activities Report 2013
3 (ASX: KGM) 26 October 2016. KalNorth Gold Mines Limited Annual Report to Shareholders 2016
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE
27 FEBRUARY 2025
Diligence will be to confirm that near-term open pit mining and toll treatment is
achievable and the timeline to do so.
The Company’s focus has been on mining aspects of the Project but the exploration
potential in the tenement package may be considerable and a preliminary
assessment will be made during Due Diligence.
Figure 2. Lindsays Mine Site Layout.
(AIM: KRS) 19 December 2016. Keras Resources PLC Annual Report 2016
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE
27 FEBRUARY 2025
Competent Person Statement
The information in this announcement that relates to production and resources for
the Parrot Feathers and Trial Pits in the Lindsay’s Project is extracted from the
following reports:
(ASX: KGM) 25 October 2013. Quarterly Activities Report 2013.
(ASX: KGM) 18 October 2013. KalNorth Gold Mines Limited Annual Report to
Shareholders 2013.
(ASX: KGM) 26 October 2016. KalNorth Gold Mines Limited Annual Report to
Shareholders 2016.
(AIM: KRS) 19 December 2016. Keras Resources PLC Annual Report 2016.
The KalNorth reports are available via the following link:
https://www.delisted.com.au/company/kalnorth-gold-mines-limited
The Keras Resources report is available via the following link:
https://kerasplc.com/
The company confirms that it is not aware of any new information or data that
materially affects the information included in the original market announcements
and, in the case of estimates of Mineral Resources or Ore Reserves, that all material
assumptions and technical parameters underpinning the estimates in the relevant
market announcements continue to apply and have not materially changed. The
company confirms that the form and context in which the Competent Person’s
findings are presented have not been materially modified from the original market
announcement.
Forward Looking Statements
This Announcement may contain forward-looking statements which are identified
by words such as ‘may’, ‘could’, ‘should’, ‘believes’, ‘estimates’, ‘targets’,
‘expected’, or ‘intends’ and other similar words that involve risks and uncertainties.
These statements are based on an assessment of present economic and operating
conditions, and on a number of assumptions regarding future events and actions
that, as at the date of this Announcement, are considered reasonable. Such
forward-looking statements are not a guarantee of future performance and involve
known and unknown risks, uncertainties, assumptions, and other important factors,
many of which are beyond the control of the Company, the Directors, and the
management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking
statements contained in this Announcement will actually occur and investors are
cautioned not to place undue reliance on these forward-looking statements.
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN SECURITIES EXCHANGE
27 FEBRUARY 2025
This announcement has been approved for release by the Board of Auric Mining Ltd.
Corporate Enquiries
Investor Relations
Follow our
communications
Mark English
Managing Director
Auric Mining Limited
Alex Cowie
Director
NWR Communications
Click here to subscribe
to our updates
T +61 409 372 775
T +61 412 952 610
E menglish@auricmining.com.au E alexc@nwrcommunications.com.au
Auric Mining Limited
ACN 635 470 843