4,300 ounces of gold produced from second campaign at
Jeffreys Find Gold Mine. Toll milling continues.
Highlights
•
Approximately 4,300 ounces of gold produced from second campaign to 6
October 2023.
•
Stage One gold production now exceeds 6,000 ounces.
•
113,000 tonnes of gold ore have now been delivered to the Greenfields Mill at
Coolgardie for processing from second campaign.
•
Remaining 36,000 tonnes on Jeffreys Find ROM Pad at Norseman to be hauled
to mill during coming weeks.
•
Target to process 180,000 tonnes in total for Stage One on budget within time,
yield and budget parameters.
•
Auric hosted at Perth Mint Refinery. First cash to Auric due this month.
The Announcement
Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to announce
approximately 4,300 ounces of gold has been produced so far during the second
campaign from the stage one pit at The Jeffreys Find Gold Mine near Norseman,
WA. Total production at 6 October 2023 now exceeds 6,000 ounces.
Processing continues at The Greenfields Mill, Coolgardie. Auric’s joint venture
partner, BML Ventures Pty Ltd of Kalgoorlie, (BML) is putting through a second parcel
of around 145,000 to 150,000 tonnes of ore to complete the first stage of mining
Jeffreys Find.
The second processing campaign commenced on 10 September 2023 and is
expected to be completed early November 2023. That follows from the first
page | 1
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 10 October 2023
Auric Mining Limited (ACN 635 470 843)
processing campaign where 1,721 ounces of gold was produced from a 36,180
tonne ore parcel. 1
The Perth Mint Refinery hosted Auric Mining Ltd on Wednesday, 4 October 2023 to
showcase the refinery and processing of the Jeffreys Find Gold.
Auric staff and Cameron Alexander – General Manager Commercial Development Perth
Mint. Perth Mint Refinery, discussing gold refining. (Photo courtesy: Perth Mint)
As at 6 October 2023, around 150,000 tonnes (in total) of ore have been delivered
to Greenfields since the start of processing with the balance of about 36,000 tonnes
to be hauled over the coming two weeks.
“The first surplus cash is now spinning out the end,” said Managing Director Mark
English.
“Very soon the current parcel of between 145,000 and 150,000 tonnes will be
completely processed and gold despatched to the Perth Mint for sale. In total we
estimate over 180,000 tonnes will be processed from the stage one mining.
A first parcel of 36,000 tonnes averaged 1.58g/t and early indications are this parcel
will do better,” he said.
1 (ASX:AWJ) 25 August 2023; First Stage Mining and Processing Completed – All Gold Sold
page | 2
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 10 October 2023
Auric Mining Limited (ACN 635 470 843)
“We acquired this tenement from Mincor Resources in September 2020, only months
before our listing on the ASX. In around three years we have it producing cash. It is
a terrific result and will allow us to inject millions into our ongoing development,
principally at Munda Gold Deposit near Widgiemooltha.
Based on what we already know we expect gross revenue generated from this first
stage to be in excess of $28 million which means the partners in this project are going
to split millions in surplus cash,” said Mr English.
BML are incurring and paying all mining costs and expenses. After completing the
first stage of mining the partners will subtract all costs, including a cash retention for
the second stage pit, before splitting the surplus cash proceeds on a 50:50 basis. This
will provide Auric with a substantial cash boost, expected throughout October and
November 2023.
The entire project life is short and final mining is expected to be completed late
2024/early 2025. The project budgeted for a gold price of AUD$2,600/ounce. A
substantially higher price has subsequently placed the joint venture in a more
favourable position.
Auric will update the ASX market on production, yield, gross revenue and cash
distributions on a regular basis.
Auric Directors: Mark English, Steven Morris and John Utley. Perth Mint Refinery, holding
Jeffreys Find gold bars. (Photo courtesy: Perth Mint)
page | 3
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 10 October 2023
Auric Mining Limited (ACN 635 470 843)
Forward Looking Statements
This Announcement contains forward-looking statements which are identified by
words such as ‘may’, ‘could’, ‘should’, ‘believes’, ‘estimates’, ‘targets’, ‘expected’,
or ‘intends’ and other similar words that involve risks and uncertainties. These
statements are based on an assessment of present economic and operating
conditions, and on a number of assumptions regarding future events and actions
that, as at the date of this Announcement, are considered reasonable. Such
forward-looking statements are not a guarantee of future performance and involve
known and unknown risks, uncertainties, assumptions, and other important factors,
many of which are beyond the control of the Company, the Directors, and the
management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking
statements contained in this announcement will actually occur and investors are
cautioned not to place undue reliance on these forward-looking statements.
This announcement has been approved for release by the Managing Director.
Corporate Enquiries
Follow our communications
Mark English
Managing Director
Auric Mining Limited
+61 409 372 775
menglish@auricmining.com.au
Subscribe: auricmining.com.au
page | 4
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
Share your feedback
Discover