Grade Control Drilling at Munda Gold Project
Released
Released
Announcement PDF
ASX Announcement
auricmining
27 October 2023
ASX: AWJ | ACN 635 470 843
Grade Control Drilling at Munda Gold Project
Highlights
•
Grade control drilling program at Munda Gold Project near Widgiemooltha,
Western Australia, to start 1 November 2023.
•
Approximately 380 holes for 11,500 metres to be drilled on a 10m x 10m grid
pattern over a planned Stage 1 pit.
•
Program will significantly de-risk the project.
•
Other mine-planning activities in progress.
•
Target is to mine a starter pit in late 2024.
The Announcement
Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to announce an
update on the Munda Gold Project near Widgiemooltha, Western Australia.
Grade Control Program
Grade control drilling is scheduled to get underway at the Munda Gold Project on
1 November 2023. This is another significant step towards open-pit mining of the
deposit and follows on from a recent Scoping Study which defined a Production
Target of between approximately 1.67Mt at 2.2g/t Au and 2.18Mt @ 1.9g/t
producing between 112,000oz and 129,100oz of gold. 1
The grade control program comprises approximately 380 holes for 11,500 metres on
a 10m x 10m grid pattern. The drill pattern covers the starter pit defined in the
Scoping Study within a larger area of near surface mineralisation (Figure 1).
1 (ASX: AWJ) 28 June 2023: Positive Scoping Study for Munda Gold Project
page | 1
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 27 October 2023
Auric Mining Limited (ACN 635 470 843)
Auric have contracted Kalgoorlie-based Total Drilling Services Pty Ltd (TDS) to
undertake the drilling.
“There are some complex geological elements within the deposit. Results from the
drilling program will help us better understand these elements and the resultant gold
distribution. This will aid in significantly de-risking the project and allow us to plan the
next steps” said Auric’s Managing Director Mark English.
“A Scoping Study for Munda completed mid-year shows us a path to more than $75
million free cash for a mine lasting three years. It’s our aim to have a starter pit
producing gold in 2024 before expanding the mine in 2025 and beyond,” said Mr
English.
Figure 1. Munda optimised pit outline, starter pit and existing trial pit with proposed grade
control drill holes.
Work Completed
The Munda Gold Project is at an early development stage:
page | 2
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 27 October 2023
Auric Mining Limited (ACN 635 470 843)
•
Preliminary metallurgical testwork undertaken by Auric reported a gold
recovery of 96.6%. 2 Further metallurgical testwork is planned.
•
A Scoping Study for open-pit mining and third-party toll treatment returned a
positive result showing that at gold prices from AUD2,400/oz to AUD2,800/oz,
the Production Target for the Project ranges from approximately:
˗
˗
•
1.67Mt at 2.2g/t producing 112,000 oz gold; to
2.18Mt at 1.90g/t producing 129,100 oz gold.
The adopted base case scenario at AUD2,600/oz details mining approximately
1.72Mt to generate an undiscounted accumulated cashflow surplus of $76.9M.
This was predicated on utilising a single third-party processing plant operating
under a toll treatment agreement, located approximately 82km from Munda
Gold Project.
Next Steps
The positive outcome from the Scoping Study justifies more detailed mine planning
and potentially mine permitting which will be based on the following activities:
•
An updated resource model and definition of an optimal grade control drill
pattern for mining utilising results from the 10m x 10m resource definition and
grade control program;
•
Geotechnical and hydrological studies;
•
Additional metallurgical testwork;
•
A topographic survey;
•
Waste rock characterisation;
•
Fauna and vegetation surveys; and
•
Updated cost estimates for grade control, mining, drill and blast, and haulage.
Auric has commenced much of this work and engaged the appropriate
consultants.
It is expected the grade control drilling program will take around 6 weeks. Results will
be announced to the market throughout the program when received.
This announcement has been approved for release by the Board.
Corporate Enquiries
Follow our communications
Mark English
Managing Director
Auric Mining Limited
+61 409 372 775
menglish@auricmining.com.au
Subscribe: auricmining.com.au
2 (ASX: AWJ)11 May 2022: Exceptional Result with Munda Preliminary Metallurgical Testwork Returning 96.57% Gold Extraction
page | 3