Toll Milling Commenced
From Jeffreys Find Gold Mine
Highlights
•
Toll milling of ore from the Jeffreys Find Gold Mine commenced on 19 July 2023.
•
Initial batch of approximately 30,000 tonnes expected to be processed by the
end of July.
•
First gold to be poured within days.
•
More than 100,000 tonnes of gold ore on ROM Pad at Jeffreys Find mine
awaiting transport to mill.
The Announcement
Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to announce
that toll milling of the first batch of approximately 30,000 tonnes of ore from its
Jeffreys Find Gold Mine has now commenced. It is being processed by the
Greenfields Mill at Coolgardie.
Auric Mining has now reached a landmark moment as a maiden gold pour is
expected within days.
“In less than three years since listing on the ASX we have become one of Western
Australia’s gold producers. This is a first-class result for Auric and its partner, BML
Ventures Pty Ltd (BML) of Kalgoorlie,” said Auric’s Managing Director Mark English.
“Once the first batch has been processed through the mill, we will be able to
reconcile gold recovered against the grade control model greatly adding to
confidence in the project economics. That is only weeks away,” he said.
“Meanwhile BML have now stockpiled more than 100,000 tonnes of ore at the mine
site near Norseman, awaiting transport to the mill. This project is right on track to
achieve our ambition of mining and processing 150,000 to 180,000 tonnes from the
mine, in the first phase,” said Mr. English.
page | 1
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 20 July 2023
Auric Mining Limited (ACN 635 470 843)
More than 100,000 tonnes of gold ore is now sitting on the ROM pad at Jeffreys Find.
The total project life is short and final mining is expected to be completed by the
end of 2024. The project budgeted on a gold price of AUD$2,600/ounce. A
consistently higher gold price has now placed the joint venture in a more favourable
position.
Open pit mining at the Jeffreys Find Gold Mine.
page | 2
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 20 July 2023
Auric Mining Limited (ACN 635 470 843)
Forward Looking Statements
This Announcement contains forward-looking statements which are identified by
words such as ‘may’, ‘could’, ‘should’, ‘believes’, ‘estimates’, ‘targets’, ‘expected’,
or ‘intends’ and other similar words that involve risks and uncertainties. These
statements are based on an assessment of present economic and operating
conditions, and on a number of assumptions regarding future events and actions
that, as at the date of this Announcement, are considered reasonable. Such
forward-looking statements are not a guarantee of future performance and involve
known and unknown risks, uncertainties, assumptions and other important factors,
many of which are beyond the control of the Company, the Directors, and the
management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking
statements contained in this announce will actually occur and investors are
cautioned not to place undue reliance on these forward-looking statements.
Mark English
Managing Director
This announcement has been approved for release by the Board.
Further information contact:
Mark English |0409 372 775
menglish@auricmining.com.au
page | 3
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
Share your feedback
Discover