Positive Scoping Study for Munda Gold Project
Released
Released
Announcement PDF
A S X A nn oun c em en t
28 June 2023
ASX: AWJ | ACN 635 470 843
auricmining
Positive Scoping Study for Munda Gold Project
Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to present the range of
outcomes of a Scoping Study for open-pit mining and third-party toll treatment of the
Munda gold deposit, (Munda or the Project) which is located 98km south of Kalgoorlie in
Western Australia.
The positive results of this Scoping Study justify further work to refine material inputs and
enhance project economics for the Munda gold deposit.
Important Note
The Scoping Study referred to in this announcement has been undertaken to determine the
viability of open pit mining and third-party toll treatment of the Munda gold deposit within
the Widgiemooltha Gold Project. It is a preliminary technical and economic study of the
potential viability of the Project. It is based on low level technical and economic
assessments that are not sufficient to support estimation of ore reserves. Further evaluation
work and appropriate studies are required before Auric will be in a position to estimate any
ore reserves or to provide any assurance of an economic development case.
The Scoping Study is based on the material assumptions outlined below. These include the
availability of funding. While Auric considers all of the material assumptions to be based on
reasonable grounds, there is no certainty that they will prove to be correct or that the range
of outcomes indicated by the Scoping Study will be achieved.
To achieve the outcomes indicated in this study funding of the order of $4.7 million to $9.7
million will likely be required. Investors should note that there is no certainty that Auric will be
able to raise working capital when needed. It is also possible working capital may only be
available on terms that may be dilutive to or otherwise affect the value of Auric’s shares.
It is also possible that Auric could pursue other ‘value realisation’ strategies such as a sale,
partial sale or joint venture of the Project. If it does, this could materially reduce Auric’s
proportionate ownership of the Project.
Given the uncertainties involved, investors should not make any investment decisions based
solely on the results of the Scoping Study.
page | 1
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
Highlights
•
A single third-party processing plant operating under a toll treatment agreement was
considered. This processing plant is located approximately 82km from Munda. A range
of outcomes were defined based on gold price.
•
At gold prices from AUD$2,400 to AUD$2,800/oz, the Production Target for the Project
ranges from approximately:
•
•
1.67Mt at 2.2g/t producing 112.0koz gold, to
2.18Mt at 1.9g/t producing 129.1koz gold.
•
The Production Target generates an undiscounted accumulated cash surplus after
payment of all working capital costs, but excluding pre-mining capital requirements,
of approximately $54.7M to $101.4M.
•
Mining is contemplated over an approximately 3-year period (13 calendar quarters).
•
Pre-mining capital and start-up costs are estimated to be approximately $0.8M to
$1.7M.
•
Working capital requirements of approximately $3.9M to $8.1M were estimated based
on a Stage 1 starter pit design which would have a mine life of less than 3 months.
•
Sensitivity of the Base Case scenario to gold price was assessed. Results suggest that
project economics are robust for a broad range of gold prices.
Auric’s Managing Director Mark English commented:
“The Scoping Study highlights the value and viability of the Munda Gold Deposit.
We now have a roadmap to plan gold mining at Munda. There is still more to be done, but
this Scoping Study provides us with a high level of confidence to proceed to mining.
The independent Scoping Study highlights significant accumulated cashflow for the Munda
Project. The adopted base case scenario at AUD $2,600 per ounce details mining
approximately 1,716Mt to generate an accumulated undiscounted cashflow surplus of
$76.9 million, a terrific outcome for Auric. We will continue the planning and development
requirements quickly.”
page | 2
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
Figure 1. Munda Gold Deposit Location Plan.
page | 3
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
Executive Summary
Auric commissioned Minecomp Pty Ltd, a Kalgoorlie based consulting firm with extensive
experience evaluating mining projects in the Eastern Goldfields, to undertake a Scoping
Study evaluating potential open pit mining at Munda and ore processing via toll treatment
at an existing plant.
The processing plant considered for this study is located near Coolgardie, approximately
82km from Munda. It will soon be toll milling ore from Auric’s Jeffreys Find gold deposit under
the terms of a toll milling agreement.
Minecomp’s study included generating optimal pits and a Stage 1 Starter Pit design utilising
Whittle and Surpac optimisation software and mine planning software. The study is based
on the January 2022 FSSI MIK recoverable resource model described in an announcement
to the ASX on 28 January 2022 1. The resource model was prepared by a competent person
in accordance with the 2012 JORC code and includes estimates classified as Indicated and
Inferred.
•
Based upon the resource estimate model, slope parameters and the cost structure
applied, the Production Target at gold prices AUD$2,400 and AUD$2,800/oz, ranges
from approximately:
o
1.67Mt at 2.2g/t producing 112.0koz gold recovered and an undiscounted
accumulated cash surplus of $54.7M, to
o
2.18Mt at 1.9g/t producing 129.1koz gold recovered and an undiscounted
accumulated cash surplus of $101.4M
Project sensitivities were examined for a range of gold prices demonstrating that Project
economics are robust with positive outcomes returned for gold prices ranging from
AUD$1,000 to AUD$4,000 per ounce.
A Base Case at AUD$2,600 per ounce gold price was used to assess the components of
Inferred and Indicated Mineral Resources. The Production Target at the Base Case is
approximately:
o
1.716Mt at 2.2g/t producing 114.7koz gold recovered and an undiscounted
accumulated cash surplus of $76.9M
Approximately 84% of the total Production Target resulting from the Scoping Study is based
on Indicated Mineral Resources, and approximately 16% is based on Inferred Mineral
Resources. There is a low level of geological confidence in Inferred Mineral Resources and
there is no certainty that further drilling will result in the determination of Measured or
Indicated Mineral Resources or that the Production Target will be realised. Although some
of the Inferred Mineral Resources occurs at shallow depths, there is sufficient, easily mined
and readily accessible Indicated Mineral Resources within the optimum shell to enable the
impact of any Inferred Mineral Resources to be insignificant. Inferred Mineral Resources do
not feature early in the conceptual mine plan. The Inferred Mineral Resources contributing
to the Production Target are not the determining factor in project viability.
No allowance was made for capital or start-up costs in the optimisation analysis. The capital
and start-up costs are comprised of the costs associated with, but not limited to mobilisation,
1 (ASX;AWJ) 28 January 2022; Increase in Estimated Resources at Munda and Reclassification from Inferred to Indicated
page | 4
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
site establishment, pre-mining earthworks, access and haulage road and demobilisation.
These costs have been estimated for the purposes of the Scoping Study at approximately
$1.25M and can be represented as a range from $0.8M to $1.7M to reflect the accuracy of
cost parameters used in the study which is considered to be +/- 35%.
To estimate working capital requirements, an approach was taken to produce a starter pit
design which was evaluated using the same cost and revenue assumptions, with the total
operating costs less the processing costs allocated as working capital. This Stage 1 pit is
estimated to have a mine life of less than 3 months.
Based upon this approach the total working capital requirements were estimated to be
approximately $6.0M and can be represented by a range from $3.9M to $8.1M to reflect
the limited accuracy of cost parameters used in the study.
To achieve the range of outcomes indicated in the Scoping Study, funding of the order of
$7.2M ($4.7M to $9.7M) will likely be required for capital, start-up costs and working capital
requirements.
Material Assumptions and Modifying Factors
The Scoping Study, and Production Targets derived from the study are based on the
material assumptions and modifying factors described in the following notes and in the
appended JORC (2012) Table 1. Auric’s evaluation of the Project is at an early stage, and
although there are reasonable grounds for these assumptions, they represent low level
technical assessments that are not sufficient to support the estimation of Ore Reserves, or
to provide assurance of an economic development case at this stage, or to provide
certainty that the conclusions of the Scoping Study will be realised.
Material assumptions and modifying factors underpinning the Scoping Study comprise the
following:
•
The Multiple Indicator Kriged (MIK) resource estimate model was provided by FSS
International Consultants (Australia) Pty Ltd. At a 0.5g/t cut-off, the resource estimate
was:
Cut-off
(Au g/t)
0.5
Resource
Category
Tonnes
(million)
Au
(g/t)
Au
(koz)
Indicated
3.68
1.38
163.1
Inferred
0.80
1.39
35.6
Total
4.48
1.38
198.7
Table 1. Munda – January 2022 Mineral Resource Estimate at 0.5g/t cut-off.
•
Auric does not hold the nickel or lithium rights at Munda and there is some coincident
gold and nickel mineralisation. In keeping with a conservative approach, zero gold
grade was assigned to any gold ore blocks which graded 1% nickel or greater. The
assumption is that any >1% nickel blocks mined as a consequence of mining the
production target would be placed on a separate ore stockpile and no gold
recovered from that stockpile. This approach excluded approximately 51,000t at
2.2g/t for 3.6koz gold from the optimal AUD $2,600 pit.
page | 5
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
•
The resource estimate model is a recoverable resource model and as such, no
additional allowances are made for mining dilution and ore loss.
•
Bulk densities were determined by water displacement method on drill core. The bulk
densities as incorporated into the supplied resource estimate model were:
Regolith
Bulk Density
Oxidised
2.20
Transitional
2.50
Fresh
2.75
Table 2. Munda – Bulk Densities.
A bulk density dataset that accounts for spatial, lithological and weathering
variations continues to be built and will lead to further refinement of the bulk density
values used. At this stage, the bulk density values used in the resource estimates are
considered conservative.
•
The gold price of AUD $2,600/oz is also considered conservative. It was selected for
the base case with reference to the gold price through 8 months from November 2022
to June 2023 over which period the minimum price was AUD$2,599 per ounce and
the maximum was AUD$3,056 per ounce. Sensitivity to gold price was assessed by
evaluating the Mineral Resources for a gold price range of between AUD$1,000/oz
and AUD$4,000/oz in $100 increments.
•
The study includes the Western Australian State Government royalty of 2.5% of
revenue applied to gold production in the state. No other royalties apply to Munda.
•
The Scoping Study incorporates a metallurgical recovery of 95% regardless of regolith.
These figures are based upon metallurgical test work completed for Auric by Upside
Metallurgy and announced to the ASX on 11 May 2022 2.
•
No allowances have been made for capital and start-up costs in the optimisation
analysis. The capital and start-up costs are comprised of but not limited to the costs
associated with pre-mining grade control and resource definition drilling, mobilisation,
site establishment, pre-mining earthworks, access and haulage road construction and
demobilisation. These costs were estimated by Minecomp, on the basis of
considerable current experience in the region and first-pass evaluations of the specific
requirements for Munda. Resource definition drilling and pre-mining grade control
associated with detailed design and mining of a stage 1 pit forms a substantial
component of the costs.
•
Operating mining costs, including grade control costs are based on Minecomp’s cost
database for comparable projects reflecting extensive recent experience of
comparable projects. They reflect conventional truck and excavator open pit mining,
utilising nominally Caterpillar 777 (approximately 90 tonne capacity) dump trucks and
associated ancillary equipment.
2 (ASX: AWJ) 11 May 2022; Exceptional Result with Munda Preliminary Metallurgical Testwork Returning 96.57% Gold
Extraction
page | 6
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
•
No minimum mining widths were applied, however, the resource model assumes a 5m
minimum width.
•
Overall wall angles of 45 degrees were deemed applicable for first pass optimisation
in similar geological settings and including perceived ramp configurations applicable
to a 777-haulage truck mining fleet. Further geotechnical investigations are required
and will be undertaken as study work progresses.
•
Haulage costs reflect approximate costs of ore cartage from Munda to a processing
plant located approximately 82km from Munda along existing roads after exit onto
the Coolgardie-Esperance Highway.
•
Processing and administration costs reflect Minecomp’s extensive recent experience
of comparable projects, and Auric’s preliminary assessment of processing costs for
toll-treating. Auric has not entered into any formal agreement, or detailed discussions
with processing plant operators.
•
The Scoping Study assumes open pit mine development comprises several mining
stages developing an ultimate pit reflecting the base case optimal pit shell generated
by the Scoping Study. This optimal pit shell extends over a length of approximately
690m, width of approximately 350m and reaches a maximum depth of approximately
120m. The Stage 1 pit, for which Minecomp produced a first-pass pit design extends
over approximately 150m in length to a maximum depth of around 30m.
•
The proposed mining area lies within Mining Lease M15/87. A Miscellaneous Licence,
L15/414, for an ore haulage road has been granted. The ore haulage road will link
Munda to the Coolgardie-Esperance Highway, a distance of approximately 4.8km.
•
Fauna and flora studies as well as surface and groundwater studies and a detailed
topographic survey will need to be completed as a component of permitting
applications and statutory approval for mining.
•
The proposed mining operation will not include any on-site storage of tailings. Waste
rock as Munda is typically non-acid forming. There is not expected to be any
environmental impacts of significance.
•
Two heritage surveys were completed prior to the 1999 development of the Resolute
trial pit and no heritage sites were recorded. The site will need to be reassessed in
terms of recent legislation but there is no reason to expect any issues in terms of
heritage.
The cost parameters used for the study are considered to have an accuracy of +-35%.
Pre-mining costs ($1,000)
Capital and start-up costs
Mobilisation
$ 150
Site establishment (offices, workshops etc)
$ 350
Mining establishment, ore pad, waste dump
$ 500
Haul road construction
$ 100
Demobilisation
$ 150
Total
$1,250
page | 7
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
Working capital costs ($1,000)
Mining
$2,570
Grade Control
$1,700
Haulage costs
$1,428
Administration
$ 296
Total
$5,995
Revenue parameters
Gold price per ounce
$2,600
Western Australian State Government Royalty
2.5%
Metallurgical recovery
95%
Summary of unit operating costs
Average mining costs per BCM (all material)
Mining (load, haul, dump)
$6.33
Blasting
$2.80
Ancillary extra costs
$2.30
Rehabilitation
$0.18
Total
$11.61
Costs per tonne of material processed
Grade Control
$ 3.00
Haulage (82km)
$14.48
Treatment
$50.00
Administration
$ 3.00
Total
$70.48
Table 3. Munda Scoping Study Material Assumptions.
Study Results and Production Target
The results of the study are positive and justify Auric committing to further work to refine
material inputs and enhance project economics.
A Production Target derived from the Scoping Study is shown below. These approximate
figures represent the potentially economic portions of the Mineral Resource based on the
cost and revenue assumptions summarised in Table 3 and constrained to a base case
Scoping Study optimal pit shell for a toll treatment haulage scenario.
The Production Target includes Inferred Mineral Resources for which there is a low level of
geological confidence. There is no certainty that further drilling will result in the
determination of Measured or Indicated Mineral Resources or that the Production Target
will be realised.
The Base Case Production Target for the approximately 82km haulage base case option is
estimated to comprise the following:
page | 8
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
1.716Mt at 2.2g/t for 114.7koz gold recovered and an undiscounted accumulated cash
surplus of $76.9M. These Mineral Resource tonnes are mined in conjunction with
approximately 7,364k BCM of sub-grade and waste representing a stripping ratio of 11.5:1.
The cost and revenue assumptions used to define the Production Target were also applied
to a Stage 1 design pit. The Production Target for the Stage 1 design pit is estimated to
comprise the following:
Approximately 98.7kt @ 2.4g/t for 7.2koz gold recovered and an undiscounted
accumulated cash surplus of $7.3M. The corresponding stripping ratio is 5.4:1
No Inferred Mineral Resources are included in the Production Target for the Stage 1 pit.
Approximately 84% of the Production Target resulting from the Scoping Study is based on
Indicated Mineral Resources and approximately 16% is based on Inferred Mineral Resources.
Although some of the Inferred Mineral Resources occur at shallow depths, there is sufficient,
easily mined and readily accessible Indicated Mineral Resources within the optimal shell to
enable processing of any Inferred Mineral Resources to be deferred to the latter stage
(starting Quarter 10) of the project. This is illustrated in Figure 2 which represents a mining
schedule on a quarterly basis for the Production Target. As such, the Inferred Mineral
Resource contribution to the Production Target is not the determining factor in project
viability.
MUNDA
Ore Processed by Resource Category
Processed Ore Tonnage (t)
160,000
140,000
120,000
100,000
80,000
60,000
40,000
20,000
0
1
2
3
4
5
6
7
8
9
10
11
12
13
Calendar Quarter
Tota l Proces s ed
Indi ca ted
Inferred
Figure 2. Base Case Production Target Quarterly Mining Schedule by Resource Category.
The total project has an estimated mine life of approximately 3 years with processing time
potentially longer, dependent on mill availability. This is estimated to give an undiscounted
accumulated cash surplus after payment of all working capital costs of approximately
$76.9M.
The AUD$2,600 pit crest and corresponding cross section are shown in Figures 3 and 4.
page | 9
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
Figure 3. Munda Gold Deposit Optimised Pit Plan Over Geology.
Figure 4. Munda Gold Deposit Cross Section Through Optimised Pit (refer Figure 3).
page | 10
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
Sensitivity Analysis
The Scoping Study included sensitivity analysis assessing the impact of gold price on
Production Target estimates by generating optimal pits for a range of gold prices from
AUD$1,000/oz to AUD$4,000/oz.
The results of this analysis are summarised in Figure 5, which shows the change in Production
Target tonnes and ounces with gold price and in Figure 6, which shows the change in
operating profit and cash cost per ounce of gold produced with gold price. The Production
Targets are shown as profitable for the full range of gold prices.
3,500,000
180,000
3,000,000
160,000
140,000
2,500,000
120,000
2,000,000
100,000
1,500,000
80,000
60,000
1,000,000
40,000
500,000
Contained Ounces (oz)
Produc�on Target (t)
Produc�on Target and Contained Ounces versus Gold Price
20,000
0
4,000
3,800
3,600
3,400
3,200
3,000
2,800
2,600
2,400
2,200
2,000
1,800
1,600
1,400
1,200
1,000
0
Gold Price ($/oz)
Produc�on Ta rget (t)
Conta i ned Ounces
Figure 5. Production Target Tonnage and Corresponding Contained Gold Sensitivity to Gold Price.
Opera�ng Profit and Cash Cost per Ounce versus Gold Price
2,500
Opera�ng Profit ($)
250,000,000
2,000
200,000,000
1,500
150,000,000
1,000
100,000,000
500
50,000,000
4,000
3,800
3,600
3,400
3,200
3,000
2,800
2,600
2,400
2,200
2,000
1,800
1,600
1,400
1,200
0
1,000
0
Cash Cost per Ounce ($)
300,000,000
Gold Price ($/oz)
Opera �ng Profit
Ca s h Cos t per Ounce
Figure 6. Operating Profit and Corresponding Cash Cost Sensitivity to Gold Price.
page | 11
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
Compliance Statements
The information in this announcement relating to the current resource estimate for the
Munda gold deposit is extracted from the announcement Increase in Estimated Resources
at Munda and Reclassification from Inferred to Indicated dated 28 January 2022 and is
available to view on the Auric website, auricmining.com.au. The company confirms that it
is not aware of any new information or data that materially affects the information included
in the original market announcement and, that all material assumptions and technical
parameters underpinning the estimates in the relevant market announcement continue to
apply and have not materially changed. The company confirms that the form and context
in which the Competent Person’s findings are presented have not been materially modified
from the original market announcement.
The information in this announcement relating to metallurgy of the Munda gold deposit is
extracted from the announcement Exceptional Result with Munda Preliminary Metallurgical
Testwork Returning 96.57% Gold Extraction dated 11 May 2022 and is available to view on
the Auric website, auricmining.com.au. The company confirms that it is not aware of any
new information or data that materially affects the information included in the original
market announcement and, that all material assumptions and technical parameters
underpinning the estimates in the relevant market announcement continue to apply and
have not materially changed. The company confirms that the form and context in which
the Competent Person’s findings are presented have not been materially modified from the
original market announcement.
The information in this report that relates to the Open Pit Mining Scoping Study for Munda
and to Production Targets derived from the Study is based on information compiled by Mr
Gary McCrae, a Competent Person who is a Member or Fellow of The Australian Institute of
Mining and Metallurgy and a full time employee of Minecomp Pty Ltd. Mr McCrae has
sufficient experience which is relevant to the style of mineralisation and type of deposit
under consideration and to the activity which he is undertaking to qualify as a Competent
Person as defined in the 2012 edition of the “Australasian Code for Reporting Exploration
Results, Mineral Resources and Ore Reserves”. Mr McCrae consents to the inclusion in the
report of the matters based on his information in the form and context in which it appears.’
page | 12
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
Forward Looking Statements
This Announcement contains forward-looking statements which are identified by words
such as ‘may’, ‘could’, ‘should’, ‘believes’, ‘estimates’, ‘targets’, ‘expected’, or ‘intends’
and other similar words that involve risks and uncertainties. These statements are based on
an assessment of present economic and operating conditions, and on a number of
assumptions regarding future events and actions that, as at the date of this Announcement,
are considered reasonable. Such forward-looking statements are not a guarantee of future
performance and involve known and unknown risks, uncertainties, assumptions and other
important factors, many of which are beyond the control of the Company, the Directors
and the management. The Directors cannot and do not give any assurance that the results,
performance or achievements expressed or implied by the forward-looking statements
contained in this announce will actually occur and investors are cautioned not to place
undue reliance on these forward-looking statements.
Mark English
Managing Director
This announcement has been approved for release by the Board.
Further information contact:
Mark English
menglish@auricmining.com.au
page | 13
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 28 June 2023
Auric Mining Limited (ACN 635 470 843)
Appendix A: JORC (2012) Table 1 Checklist
Material Assumptions and Modifying Factors
*Note: The following criteria are shown to better define material assumptions used in the Scoping Study
– No Ore Reserves are estimated.
Item
Criteria
Commentary
1
Mineral Resource
estimate used for
assessment of
potential Production
Target
•
•
No Ore Reserves are estimated as part of the Munda Scoping Study.
For the purposes of this Scoping Study, the Mineral Resource estimate
model used was titled Munda_MIK_Model_Updated. This model was
generated by FSS International Consultants (Australia) Pty Ltd (FSSI) and was
deemed to be a recoverable resource model. This Mineral Resource
estimate was prepared by a Competent Person in accordance with the
JORC Code, 2012 Edition.
2
Parties participating in
the Scoping Study
and site visits
•
The following parties have provided input to this Scoping Study:
• Minecomp Pty Ltd coordinated the mining study work and the
compilation of the economic model for the project. Minecomp were
engaged as an independent consultant by Auric Mining Limited to assist
with the Scoping Study.
• FSSI compiled the Mineral Resource estimate model upon which this
Scoping Study is based.
• No site visits were undertaken by the Competent Person as it was
considered that site visits would not materially affect the findings of the
Scoping Study.
3
Study status
•
The type and level of study is a Scoping Study as defined in Section 38 of the
JORC Code, 2012 Edition.
The Scoping Study has not been used to convert Mineral Resources to Ore
Reserves. The Mineral Resource is deemed a recoverable resource and as
such allowance for modifying Factors have been incorporated.
Cut-off grades were determined by Whittle optimisation software.
The following inputs were used to estimate revenue per gram of gold
produced:
• Gold price: A$2,600/oz
• Gold metallurgical recovery: 95%
• WA State Royalty payable on gold revenue: 2.5%
The following inputs were used to estimate operating cost per tonne of ore
treated: • Mining cost
• Ore Haulage and Processing cost
• General & Administration costs
•
4
Cut-off parameters
used in potential mine
analysis
•
•
•
5
Mining factors or
assumptions used in
the Scoping Study
•
•
•
•
•
•
•
•
•
No conversion of the Mineral Resource to Ore Reserves.
The Mineral Resource model has been built as a recoverable resource
model which incorporates mining dilution and ore loss.
Mining method is conventional open pit with drill and blast, excavate, load
and haul. The mineralized zone geometry coupled with the low stripping
ratio indicate that Munda is most suited to mining by conventional open pit
mining methods.
Pit slope angles and berm and batter configurations have been based upon
those existing open pits which mine mineral resources of similar geometries
and similar geological settings.
No minimum mining widths have been applied, however the Resource
model assumes a 5m minimum width.
Inferred Resources were included in the Scoping Study
Further geotechnical investigation and assessment will be completed as the
stud