Quarterly Activities Report
Released
Released
Announcement PDF
Quarterly
Activities
Report
31 March 2025
•
Quarterly Report 31 March 2025
2
Highlights
Jeffreys Find Gold Mine
•
Stage Two mining at Jeffreys Find is complete with more than 17,900 ounces gold produced so
far. Combined with Stage 1 production, the mine has produced 27,642 ounces with further
processing planned.
•
Processing of the approximately 60,000t of ore remaining at Jeffreys Find will commence in
early July 2025, at the Three Mile Hill Plant at Coolgardie.
•
Auric’s has received $8.1M from share of gold sales with Stage 2 on target to deliver $11-12
million cash surplus to Auric. Gold has been sold into a steadily rising gold price environment
with latest gold sold at $4,625 per ounce.
Munda Gold Project
•
Munda Starter Pit Mining Proposal and Mine Closure Plan have been approved by DEMIRS
and Mining Operation Notification acknowledged. Site preparation including haul road access,
waste dump, site office and ROM pads is underway.
•
Mining personnel have been employed by Auric and mining fleet hired. Auric will mine Munda
in its own right.
•
Contracts have been executed for drill and blast and key suppliers.
•
Mine camp for 12 people established a short distance from Munda.
Lindsay’s Acquisition
•
Auric has executed a Binding Letter Agreement to purchase the Lindsay’s Project from Top
Global Mining.
•
The Project is located 50km northeast of Kalgoorlie, and comprises 8 tenements, including 3
mining leases covering 33km2.
•
Open pit mining, including the Parrot Feathers deposit, was undertaken in 2013, ending
abruptly with a sudden fall in gold price and only approximately 25% of planned production
completed.
•
Potential for near-term open pit mining and toll treatment to produce gold and revenue.
•
Total purchase price is $4M being a combination of cash and shares, plus a royalty.
Quarterly Report 31 March 2025
3
Loded Dog Acquisition
•
Auric has purchased five tenements from Loded Dog Prospecting Pty Ltd in the highly
prospective Higginsville area, a short distance from Widgiemooltha.
•
The five tenements represent the first tranche of an eight-tenement package in that area,
covering 113km2
•
Included in the five tenements are brownfields ie, advanced prospects at Foote’s Find and
Amorphous.
•
The entire package will be acquired with payment of $475,000 plus milestone payments and a
royalty on production.
Burbanks Mill
•
Due diligence for the purchase of the Burbanks Plant and associated assets has been
completed. Auric intends to proceed to complete the acquisition.
• Settlement will take place once various outstanding issues are resolved and finalisation and
execution of all legal agreements. Auric expects that settlement will be sometime in late Q2
2025.
Corporate
•
The Company reported a strong financial position with $7.5 million in cash at the end of the
quarter.
• Current issued capital as at today is 148,953,371 shares.
Quarterly Report 31 March 2025
The Announcement
4
Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to report on its activities
during the 31 March 2025 Quarter and up to the date of this report.
Managing Director, Mark English said: “The March quarter saw us gather momentum on our
transformation into a gold developer and gold miner.
“At Jeffreys Find our JV partner, BML Ventures of Kalgoorlie, concluded mining on 28 January
2025, thus completing more than two years of operations. Ore was processed at two Coolgardie
Mills – The Three Mile Hill Mill and the Greenfields Mill.
“By the end of the quarter total production from Jeffreys Find mine reached 27,653 ounces of gold.
The Project looks certain to surpass more than 30,000 ounces as we have 60,000 tonnes remaining
to be processed at the beginning of July at the Three Mile Hill Mill. Gold sales for the entire Project
also surpassed $100 million during the quarter.
“At Munda, we progressed towards open pit mining of a Starter Pit. The Company executed a
contract to dry hire a mining fleet. A full mining and geological team was mobilised to site and site
preparation got underway on the 23 April.
“During the quarter Auric completed due diligence on the Burbanks Gold Facility at Coolgardie and
agreed to acquire it for $4.4 million. Completion of the transaction is expected in Q2 2025. The mill,
whilst currently inactive, provides a unique opportunity for Auric to own its own milling infrastructure
and it creates significant commercial optionality for Auric including the treatment of its own ore once
the plant is rebuilt.
“The potential for near term, open pit gold mining and toll treatment was on our minds with the
execution of a binding agreement to purchase the Lindsay’s Project, 50kms northeast of Kalgoorlie
for a total consideration of $4 million.
“The Project comprises eight tenements and three mining leases and includes the Parrot Feathers
Gold Mine from which 6,153 ounces was produced before ceasing operations in 2013. Lindsay’s
brings with it great potential to substantially grow the ounces under our control.
“In February 2025, Auric announced it was buying the Loded Dog tenements near Higginsville thus
increasing our foothold in the Widgiemooltha district and expanding our exploration targets. The
package contains brownfields and greenfields targets.
“It has been a busy and impressive quarter. We are justifiably optimistic that the work conducted in
the past few months has positioned us well to produce a lot of gold in 2025 and in the future,” said
Mr English.
Quarterly Report 31 March 2025
1.0 PRINCIPAL ACTIVITIES
5
Stage 2 mining has been completed at Jeffreys Find with no further stages planned at this time.
Approximately 60,000 tonnes of ore remain to be processed and an agreement with Focus Minerals
Limited should ensure that the ore will be processed from early July at the Three Mile Hill facility
near Coolgardie.
A total of 17,901 ounces of gold has been sold from Stage Two mining at Jeffreys Find as of 21
February 2025. Combined with production from Stage 1, 27,642 ounces has been produced from
the Jeffreys Find Gold Mine with further production pending.
Site preparations for a Starter Pit at Munda are underway following receipt of various government
approvals needed to commence operations. Auric will be mining Munda in its own right having
recruited the appropriate, experienced personnel and hired mining equipment including dump
trucks and an excavator. This represents a substantial step in Auric’s development as a miner and
producer.
Auric has executed a Binding Letter Agreement to purchase the Lindsay’s Project, including
Parrot Feathers open pit gold mine 50km northeast of Kalgoorlie. The Project comprises eight
tenements, including three mining leases, covering 33 km². Open-pit mining undertaken in 2013
ended abruptly with a sudden fall in the gold price to around A$1,300 per ounce and only
approximately 25% of the planned production was completed. The attraction for Auric is the nearterm potential for open-pit mining and toll treatment and thereby to produce gold and revenue.
Auric has purchased five tenements from Loded Dog Prospecting Pty Ltd in the highly prospective
Higginsville area, a short distance from Widgiemooltha. The five tenements represent the first
tranche of an eight-tenement package in that area, covering 113km². The acquisition complements
Auric’s ground holding in the Higginsville area.
Due diligence for the purchase of the Burbanks Plant and associated assets has been completed
and Auric intends to proceed to complete the acquisition by payment of A$4.4 million. Settlement
will take place once various outstanding issues are resolved and finalisation and execution of all
legal agreements.
Quarterly Report 31 March 2025
6
2.0 JEFFREYS FIND GOLD MINE
Through Auric’s joint venture partner BML
Ventures Pty Ltd of Kalgoorlie (BML or BML
Ventures) a total of 17,901 ounces of gold has
been sold from Stage Two mining at Jeffreys Find
as of 21 February 2025.
Ore was milled in multiple campaigns at The
Greenfields Mill, Coolgardie (Greenfields) and at
the Three Mile Hill Plant, Coolgardie (Three Mile
Hill) during 2024 and early 2025.
For Stage Two the highest gold price achieved
was A$4,625 an ounce whilst the average price
was A$4,024 per ounce.
Stage Two has generated $72.04 million in gold
sales to date versus Stage One in 2023 with
$29.28 million. Total Project gold sales have
surpassed $105 million.
There are approximately 60,000 tonnes of ore left
on the ROM Pad at the Jeffreys Find Gold Mine.
BML Ventures has executed a Toll Processing
Agreement with Focus Minerals Ltd (ASX: FML
or Focus) to process approximately 60,000
tonnes of ore at the Three Mill Hill Plant,
commencing in early July 2025. Processing is
expected to last three weeks.
Under the terms of the joint venture agreement
BML are the miners, operators and managers of
the Jeffreys Find Gold Mine. BML incurs and
pays all mining, haulage, milling costs and
related expenses. After sale of the gold, the
partners subtract all direct costs before splitting
the surplus cash proceeds on a 50:50 basis.
Interim surplus cash distributions are paid to
Auric by BML after agreement between the
partners.
On 21 February 2025 Auric received an
additional $1.5 million from BML. To date the
Company has received $8.1 million in interim
payments from BML for Stage Two with further
cash distributions to come following the final sale
of gold. BML has advised it expects Auric’s share
of Stage Two surplus cash to be in the range of
$11 million to $12 million.
Table 1. Stage Two Mining – Gold Sold
Jeffreys Find Gold Mine
Gold Recovered – Ounces
Average Sale Price per ounce
AUD
Gross Gold Revenue
Stage One
2023
Stage Two 20242025*
Total Project To
Date*
$3,006
$4,024
$3,805
$33,140,445
$72,039,320
$105,179,765
9,741
17,901
27,642
*As of 21 February 2025 interim figures only
Figure 1. Doré bar at Three Mile Hill Mill
Figure 2. Jeffreys Find Pit
Quarterly Report 31 March 2025
7
3.0 MUNDA GOLD PROJECT
Rapid progress was made at the Munda Gold Project, 5km from Widgiemooltha, Western Australia
during the quarter. A Mining Proposal and a Mine Closure Plan for a Starter Pit at Munda were
approved by the WA Government’s Department of Energy, Mines, Industry Regulation and Safety
(DEMIRS).
In anticipation of those approvals, key leadership personnel were employed including experienced
Site Senior Executives and Mine Geologists. Staff are being accommodated at a 12-man camp
established 6km from the mine site.
A grade control program over the Starter Pit extents for those holes accessible from surface on a
5m x 5m pattern was also completed. A total of 428 holes for 14,670m were drilled by Kalgoorliebased Total Drilling Services. Results have been received allowing the mine geologists to define
near surface ore blocks in advance of mining. Further grade control drilling on a 5m x 5m pattern
will be undertaken as mining exposes new benches.
Survey mark-out of the pit crest, haul road, waste dump, ROM pads and site office was completed.
Auric mobilised plant and machinery to site, including a dry hire fleet provided by MHM Contracting
Pty Ltd. The Mines Inspectorate have acknowledged Auric’s Mining Operation Notification for
Munda and site preparation is underway with clearing of extensions to the existing haul road, site
office and laydown, ROM pads and waste rock landform (Figure 3).
Figure 3. Munda Starter Pit – proposed site layout
Quarterly Report 31 March 2025
8
A Pre-feasibility study for a starter pit at Munda was reported in December 2024 1 and represents
the first step in potentially staged mining at Munda. The pre-feasibility study estimates a Probable
Ore Reserve for the Munda Starter Pit of 125,000t @ 1.8g/t for 7,400 contained ounces of gold,
producing 6,100 ounces of gold after processing.
The Company confirms that all of the material assumptions underpinning the production target or
the forecast financial information derived from a production target in the corresponding report to the
ASX dated 10 December 2024, named Munda Gold Deposit Starter Pit Ore Reserve continue to
apply and have not materially changed.
Figure 4. MHM Contracting Excavator Assembly at start of haul road extension.
Figure 5. Moxi dump trucks at accommodation camp site.
1 (ASX: AWJ): 10 December 2024. Munda Gold Deposit Starter Pit Ore Reserve
Quarterly Report 31 March 2025
4.0 LINDSAY’S FIND ACQUISITION
9
Auric has executed a Binding Letter Agreement to purchase the Lindsay’s Project, including Parrot
Feathers open pit gold mine from Top Global Mining Pty Ltd and NBC Mining Pty Ltd (The Vendors)
through their corporate advisers SEER Financial Group.
The Lindsay’s Project is located 50km northeast of Kalgoorlie, WA (Figure 6) and comprises 8
tenements, including 3 mining leases, covering 33 km². Open-pit mining undertaken in 2013 ended
abruptly with a sudden fall in the gold price and only approximately 25% of the planned production
completed.
The attraction for Auric is the potential expansion of the Company’s resource base, near-term
potential for open-pit mining and toll treatment and corresponding production of gold and revenue.
The total purchase price is $4 million, comprising $2 million (+ GST) in cash and shares to the
values of $2 million, together with a royalty of 3.5% of the Net Smelter Return from the sale of gold
from the Lindsay’s Project.
Figure 6. The Lindsay’s Project and Auric’s projects north of Widgiemooltha.
Quarterly Report 31 March 2025
10
The area has a long mining history including first gold production in 1897, a mining resurgence in the 1930’s
and small-scale mining in the late 1980’s.
KalNorth Gold Mines Limited (KalNorth) commenced modern open pit mining at Lindsay’s in January 2013
with ore processed at Saracen’s Carosue Dam mill, 70km to the east of Lindsay’s. Mining ceased in August
that same year following a drop in gold price from a high of AUD$1,625 per ounce to as low as AUD$1,295
per ounce. At that stage, KalNorth reported that 6,153oz gold was produced from 138,229t grading 1.93g/t
Au. Ore was mostly mined from the Parrot Feathers deposit with a small tonnage (1,893t) extracted from the
‘Trial Pit’ (Figure 7).
Figure 7. Lindsay’s gold mine including The Parrot Feathers open pit.
Quarterly Report 31 March 2025
11
5.0 LODED DOG ACQUISITION
Auric has purchased five tenements from Loded Dog Prospecting Pty Ltd in the highly prospective
Higginsville area, a short distance from Widgiemooltha. The five tenements represent the first
tranche of an eight-tenement package in that area, covering 113km². The acquisition complements
Auric’s ground holding in the Higginsville area.
Figure 8. Auric tenements in the Higginsville and Widgiemooltha area including Loded Dog tenure.
Quarterly Report 31 March 2025
Auric have paid $450,000 (plus GST) in cash to Loded Dog for the first tranche of 5 tenements.
12
The two parties have also agreed on milestone cash payments of $100,000 and $150,000 where gold, or gold
equivalent, resources greater than 20,000 ounces and greater than 50,000 ounces respectively are estimated
according to JORC 2012 guidelines.
In addition, Auric have agreed to a Net Smelter Royalty of 1.5% for any gold produced and a Net Smelter
Royalty for any other minerals of 0.75% to 1.5%, depending on the tenement.
The new tenements include the ‘brownfields’ Amorphous and Foote’s Find prospects and ‘greenfields’ areas
proximal to numerous former open pit and underground gold mines.
The Amorphous Prospect will provide the initial exploration focus with the potential to expand on known
mineralization extending over approximately 1km strike length (Figure 9) and including:
Hole ID
Hole Type
Results
AMC0007
RC
2m @ 10.27g/t Au from 28m
AMR0013
RAB
2m @ 8.63g/t Au from 22m
AMR0015
RAB
5m @ 5.16g/t Au from 18m
AMRC005
RC
9m @ 3.32g/t Au from 78m
AMRC006
RC
3m @ 4.38g/t Au from 45m
AMRC015
RC
7m @ 1.61g/t Au from 61m
Figure 9. Amorphous Prospect drill hole plan and geology.
Quarterly Report 31 March 2025
13
The Foote’s Find Prospect represents a second distinct target with historic drilling providing intercepts
including:
Hole ID
Hole Type
Results
FFP0010
RC
3m @ 4.65g/t Au from 30m
FFRC001
RC
3m @ 4.99g/t Au from 41m
FFRC002
RC
4m @ 3.06g/t Au from 31m
6.0 BURBANKS GOLD PROCESSING PLANT
Due diligence for the purchase of the Burbanks Plant and associated assets has been completed
and Auric intends to proceed to complete the acquisition by payment of A$4.4 million. Settlement
will take place once various outstanding issues are resolved and finalisation and execution of all
legal agreements. Auric expects that settlement will be sometime in late Q2 2025.
The plant is designed for 180,000 tpa capacity but is not currently operational. It has all requisite
infrastructure, permits and licenses including access to critical power and tails dams infrastructure
essential to the future operations of the plant. It is strategically located 15km south of Coolgardie,
WA and within trucking distance of existing Auric gold resources.
The Plant was operational up until approximately June 2019 when the operator closed the facility.
The facility requires a complete review of longer-term operations and corresponding upgrades. The
acquisition price is a substantial discount to current and replacement values. This potential
acquisition represents a clear value creation opportunity for the Company.
The acquisition will position the company for further success and growth through the direct
ownership of milling infrastructure in the WA goldfields.
7.0 OTHER EXPLORATION
No other significant exploration was undertaken during the quarter.
8.0 HERITAGE
No heritage surveys were undertaken during the quarter.
9.0 SAFETY
There were no alternate duty injuries (“ADI”) and no medically treated injuries (“MTI”) reported
during the March quarter. There were no lost time incidents (“LTI”) recorded during the quarter.
10.0 ASX COMPLIANCE
10.1 Compliance Statement
The information in this report that relates to exploration results and gold production is extracted from
the Company’s following ASX announcements which are available to view on the Company’s
website, www.auricmining.com.au:
Quarterly Report 31 March 2025
14
ASX Announcements included in the March 2025 Quarter up to date
Date
Details
14 Jan 2025
Jeffreys Find Gold Mine Stage Two Sales Exceed 14,800 Ounces
13 Feb 2025
Auric Enhances Mining Team Scaling Up To Mine Munda Starter Pit
25 Feb 2025
Auric To Acquire Loded Dog Tenements Proximal To Higginsville Gold
Deposits
24 Feb 2025
Jeffreys Find Gold Mine Gold Sales Exceed $100 Million
27 Feb 2025
Auric Executes Binding Agreement To Purchase Lindsays Project
3 Mar 2025
Jeffreys Find Gold Mine Final Toll Mill Agreement Executed
13 Mar 2025
Due Diligence Completed Auric To Acquire Burbanks Facility
1 Apr 2025
Lindsay’s Gold Project Due Diligence Period Extended
8 Apr 2025
Loded Dog Tenements Stage One Settlement Completed
14 Apr 2025
Munda Gold Mine Starter Pit Underway
ASX Announcements referred to from previous quarters
10 Dec 2024
Munda Gold Deposit Starter Pit Ore Reserve
ASX Announcements referred to from KalNorth Gold Mines Limited
25 Oct 2013
Quarterly Activities Report 2013
The Company confirms that it is not aware of any new information or data that materially affects the
information included in the original market announcements. The Company confirms that the form and
context in which the Competent Persons’ findings are presented have not been materially modified
from the original market announcements. With respect to ASX listing rule 5.3.2, the Company
confirms there were no mine production and development activities carried out by Auric for the
quarter.
All mine production and development activities at the Jeffreys Find Gold Mine are undertaken and
paid for by BML Ventures Pty Ltd. Auric is not a producer or operator. Auric only shares in cashflow
surpluses, as a silent operator, tenement and mineral rights owner.
10.2 Forward Looking Statements
This Announcement contains forward-looking statements which are identified by words such as ‘may’,
‘could’, ‘should’, ‘believes’, ‘estimates’, ‘targets’, ‘expected’, or ‘intends’ and other similar words that
involve risks and uncertainties. These statements are based on an assessment of present economic
and operating conditions, and on a number of assumptions regarding future events and actions that,
as at the date of this Announcement, are considered reasonable. Such forward-looking statements
are not a guarantee of future performance and involve known and unknown risks, uncertainties,
assumptions and other important factors, many of which are beyond the control of the Company, the
Directors and the management. The Directors cannot and do not give any assurance that the results,
performance or achievements expressed or implied by the forward-looking statements contained in
this announcement will actually occur and investors are cautioned not to place undue reliance on
these forward-looking statements.
11.0 TENEMENTS
Schedule 1 attached lists the mining tenements held at the date of this announcement, their location
and equity ownership. Auric has interests in 43 tenements.
11.1 Farm-in or Farm-out agreements
Auric is not party to any Farm-in or Farm-out agreements.
Quarterly Report 31 March 2025
15
12.0 RELATED PARTY PAYMENTS
The Company paid salaries, superannuation, annual leave and other employment entitlements to full
time employee Directors and related parties of the Company of $158,000. The Company also paid
$14,000 to Director-related parties of the Company. These costs are included in administration costs
and working capital except when technical staff are working in the field. Those direct costs are
allocated to the tenements and projects and are included at item 2.1(d) of 31 March 2025 Quarter:
Appendix 5B.
Figure 10. Auric’s projects in the Widgiemooltha-Norseman area.
Quarterly Report 31 March 2025
16
Auric Mining Ltd
Auric Mining Ltd was established to explore for and develop gold and other mineral deposits in the
Widgiemooltha-Norseman area, of Western Australia.
Auric has tenements covering 360km². Auric holds the rights to gold on all tenements, including those
held in the name of Mt Edwards Critical Metals Pty Ltd. Further, at Munda it holds all mineral rights
except nickel over a portion of the tenement, and lithium. For all other tenements, excluding those
held in the name of Mt Edwards Critical Metals Pty Ltd, Auric holds 100% of all mineral rights.
The tenements are separated into four projects (Figure 10):
The Widgiemooltha Gold Project including the Munda Gold Project
The Widgiemooltha Gold Project (“WGP”) located near the town of Widgiemooltha combines 28
tenements, including 5 granted Mining Leases. All tenements are highly prospective for gold
mineralisation.
The Jeffrey Find Gold Mine
The Jeffreys Find Gold Mine is 50km northeast of Norseman and combines 2 tenements including 1
granted Mining Lease. It includes the Jeffreys Find gold deposit where gold mineralisation extends
from the surface to at least 110m in vertical depth. The deposit is currently being mined via a joint
venture with BML Ventures Pty Ltd.
The Spargoville Project
The Spargoville Project is located 30km north of Widgiemooltha and combines 9 tenements. It lies in
the same stratigraphy, along strike from the Wattle Dam Gold Mine which produced 268,000oz gold
@ 10g/t from 2006-13; one of Australia’s highest-grade mines at that time.
The Chalice West Project
The Chalice West Project is located 50km southeast of Widgiemooltha and proximal to the Chalice
Gold Mine, a mine that produced almost 700,000 ounces of gold. The Project combines 4 tenements.
It covers 245km², including geology mirroring the Chalice Gold Mine. As well as gold, the Project is
prospective for Rare Earth Elements (REE) and for Ni-Cu and Pt-Pd deposits.
This announcement has been approved for release by the Board.
Corporate Enquiries
Investor Relations
Mark English
Managing Director
Auric Mining Limited
Alex Cowie
Director
NWR Communications
T +61 409 372 775
E menglish@auricmining.com.au
T +61 412 952 610
E alexc@nwrcommunications.com.au
Follow our
communications
Click here to subscribe to our
updates
Quarterly Report 31 March 2025
22
Schedule of Tenements
Schedule 1. The following table lists the mining tenements held at 31 March 2025 and their location.
Tenement
Project
Location
Status
Registered Holder
Mineral Rights
M15/74
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
M15/75
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
M15/698
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
M15/699
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
M15/87
Widgiemooltha
WA
Live
Widgie Gold
E15/1553
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
E15/1576
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
E15/1583
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
P15/6092
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
P15/6387
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
P15/6570
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
P15/6612
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
P15/6362
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
E15/1749
Widgiemooltha
WA
Live
Mt Edwards Critical Metals 100% Au Rights
L15/414
Widgiemooltha
WA
Live
Widgie Gold
Infrastructure
E15/1949
Widgiemooltha
WA
Live
Widgie Gold
100% All minerals
E15/1950
Widgiemooltha
WA
Live
Widgie Gold
100% All minerals
E15/1864
Widgiemooltha
WA
Pending
Mt Edwards Critical Metals 100% All minerals
E15/1929
Widgiemooltha
WA
Pending
Mt Edwards Critical Metals 100% All minerals
E15/2042
Widgiemooltha
WA
Pending
Widgie Gold
100% All minerals
E15/2043
Widgiemooltha
WA
Pending
Widgie Gold
100% All minerals
E15/2069
Widgiemooltha
WA
Pending
Widgie Gold
100% All minerals
E15/2073
Widgiemooltha
WA
Pending
Widgie Gold
100% All minerals
P15/6808
Widgiemooltha
WA
Live
Widgie Gold
100% All minerals
P15/6539
Widgiemooltha
WA
Pending
Mt Edwards Critical Metals 100% Au Rights
P15/6853
Widgiemooltha
WA
Pending
Widgie Gold
100% All minerals
P63/2279
Widgiemooltha
WA
Pending
Widgie Gold
100% All minerals
P63/2280
Widgiemooltha
WA
Pending
Widgie Gold
100% All minerals
Widgiemooltha
100% All Minerals except
Ni, Li
18
Quarterly Report 31 March 2025
Quarterly Report 31 March 2025
Tenement
23
Project
Location
Status
Registered Holder
Mineral Rights
M63/242
Jeffreys Find
WA
Live
Jeffreys Find
100% All Minerals
L63/97
Jeffreys Find
WA
Live
Jeffreys Find
Infrastructure
E15/1688
Spargoville
WA
Live
Spargoville Minerals
100% All Minerals
E15/1689
Spargoville
WA
Live
Spargoville Minerals
100% All Minerals
E15/1665
Spargoville
WA
Pending
Mt Edwards Critical Metals 100% All Minerals
E26/262
Spargoville
WA
Live
Spargoville Minerals
100% All Minerals
P15/5905
Spargoville
WA
Live
Spargoville Minerals
100% All Minerals
P15/5906
Spargoville
WA
Live
Spargoville Minerals
100% All Minerals
P15/6408
Spargoville
WA
Live
Spargoville Minerals
100% All Minerals
P15/6758
Spargoville
WA
Pending
Spargoville Minerals
100% All Minerals
M15/1899
Spargoville
WA
Pending
Mt Edwards Critical Metals 100% All Minerals
P24/5842
Spargoville
WA
Pending
Spargoville Minerals
100% All Minerals
E15/1801
Chalice West
WA
Live
Chalice West
100% All Minerals
E15/1945
Chalice West
WA
Live
Chalice West
100% All Minerals
E63/2483
Chalice West
WA
Pending
Chalice West
100% All Minerals
E63/2484
Chalice West
WA
Pending
Chalice West
100% All Minerals
Lindsay’s
WA
Pending
LMG (WA)
100% All Minerals
Jeffreys Find
Spargoville
Chalice West
Lindsay’s
E27/246
Auric Mining Limited
Level 1, 1 Tully Road
East Perth WA 6004
Australia
T +61 8 9548 9997
E info@auricmining.com.au
auricmining.com.au
ASX: AWJ
Share your feedback
Discover