Starter Pit Ore Reserve for Munda Gold Deposit
Released
Released
Announcement PDF
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
10 DECEMBER 2024
Munda Gold Deposit
Starter Pit Ore Reserve
Highlights
•
Munda Starter Pit defined for next stage in Munda Mine Development.
•
Starter Pit Reserve of 7,400 contained ounces calculated using a gold price of
AUD$3,500 per ounce.
•
Mine planning for a total of 125kt @ 1.8g/t from the Starter Pit.
•
Financial model defines Undiscounted Cashflow of $5.3M at All in Sustaining Cost
of $2,635 per ounce.
•
5 months mine life assumed, including toll treatment.
Management Comment
Mr. Mark English, Managing Director:
“This work is another key part of the process in mining Munda. We have a lot of
confidence in our approach and the key inputs that have been used. The starter pit
is designed to provide a better understanding of the deposit before aiming to go
into full production in 2026”
The Announcement
Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to announce an
Ore Reserve for a Starter Pit at Munda. The Ore Reserve is defined by a Pre-Feasibility
Study (PFS) utilising recent 10m x 10m spaced (i.e. high-density) drilling and
corresponding Indicated Resources.
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
10 DECEMBER 2024
The Ore Reserve for a starter pit at Munda represents the first step in potentially
staged mining at Munda. The Ore Reserve representative of the Starter Pit mining
plan for the Munda gold deposit is estimated as shown in Table 1.
Table 1. Munda Trial Pit Probable Ore Reserve
Proved
Probable
Tonnage
(t)
0
Grade
(g/t)
0.0
Ounces
(ozs)
0
Tonnage
(t)
125,000
Grade
(g/t)
1.8
Ounces
(ozs)
7,400
Total
Tonnage Grade Ounces
(t)
(g/t)
(ozs)
125,000
1.8
7,400
Note – Rounding errors may occur
The 125,000t of ore at a grade of 1.8g/t Au defined within the Starter Pit is comprised
entirely of Indicated Resources and is mined in conjunction with 339,000BCM of
waste rock, representing a stripping ratio of 7.6:1.
The Ore Reserve was estimated based upon extraction using owner operated
conventional open pit mining and off-site milling at a Third Party owned and
operated ore processing facility under a toll treatment arrangement. The Ore
Reserve is inclusive of modifying factors for mining dilution and mining recovery.
Contemporary in-house mining, processing and site costs have been utilised.
Key parameters defined by the Starter Pit PFS are set out in Table 2 below:
Table 2. Munda Starter Pit Pre-Feasibility
Parameter
Unit
General
Start Date
Quarter
Project Life (mining)
Months
Project Life (milling)
Months
Mining
Ore Tonnes
Kt
Grade
g/t
Contained Gold
Koz
Processing
Ore Processed
Kt
Grade
g/t
Recovery (average)
%
Gold Production
Koz
Financial
Gold Price Assumption
A$/oz
Upfront Project Capital Cost
A$M
AISC
A$/oz
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
Pre-Feasibility Study November 2024
March 2025
5.0
5.0
125
1.8
7.3
125
1.8
83
6.1
3,500
6.5
2,635
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
10 DECEMBER 2024
The financial model developed for the owner operated mining and ore processing
of the Munda Starter pit demonstrates that at a gold price of A$3,500/oz, the project
generates revenue of $21.4M and an Undiscounted Cash Flow of $5.3M at a $2,635
All in Cost Per Ounce (Table 3).
Table 3. Munda Trial Pit Pre-Feasibility Cost and Revenue Summary
Generated
Revenue
$M
21.4
Operating
Costs
$M
15.2
Capital/Startup
Costs
$M
0.65
Total
Royalties
$M
0.3
Undiscounted
Cash Flow
$M
5.3
All in Cost
Per Ounce
A$
2,635
Figure 1. Munda Starter Pit site layout.
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
10 DECEMBER 2024
Material Assumptions and Outcomes from the Pre-Feasibility Study
The Ore Reserve has been determined using the November 2024 Mineral Resource
Estimate 1 It was assumed that Auric would mine the ore and that processing would
be offsite at a third-party owned and operated processing plant located 95km from
Munda, under the terms of a toll treatment agreement.
The Pre-Feasibility Study (PFS) indicates that the Munda Starter Pit is economically
viable with an Undiscounted Cash Flow of $5.3M generated over 5 months.
The following sections further describe the material assumptions contributing to the
PFS. More detail on the material assumptions is included in Section 4 of the JORC
Table 1 Checklist attached as Appendix A.
Ore Reserve Classification
The Ore Reserve has been determined using the November 2024 Mineral Resource
Estimate. This Mineral Resource Estimate was deemed to be a recoverable resource.
Therefore, no additional allowances are required for mining dilution and mining
recovery.
Probable Ore Reserves have been derived from Indicated Mineral Resources and
constrained to the higher density (ie, 10m x 10m spaced) drilling portion of the
Mineral Resource Estimate. A ‘goodbye-cut’ at the base of the design pit is derived
from Indicated Resource which in turn is derived from 20m x 20m spaced drilling.
Mining Method and Assumptions
Mining by conventional drill and blast and load and haul open pit mining method is
considered the most suitable mining method. It was assumed that the mining fleet
will be dry-hired owner-operated and comprised of an articulated dump truck fleet
together with an 80-120t excavator and matching ancillary equipment. RC grade
control and drill and blast will be conducted by contractors.
Pit Design Parameters
The design parameters used for the Starter Pit are based on an independent
geotechnical assessment and are as follows:
1 (ASX:AWJ)10 December 2024. Munda Gold Deposit. Updated Mineral Resources. Precursor to
Starter Pit Mining Development.
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
10 DECEMBER 2024
Table 3. Munda Starter Pit Design Parameters
Level
North, East and West Walls
South Wall
N/S → 370mRL
50 degrees
55 degrees
370mRL Berm
5m wide
5m wide
370mRL → 360mRL
55 degrees
60 degrees
360mRL Berm
Nil
5m wide
360mRL → 350mRL
55 degrees
60 degrees
350mRL Berm
5m wide
5m wide
350mRL → 330mRL
65 degrees
65 degrees
Goodbye Cut
To 325mRL
Gradient
1 in 8
N/S → 370mRL
15m Wide (minimum)
Ramp
370mRL → 330mRL
8m Wide (minimum)
Switchback Diameter – 20m
Processing Method and Assumptions
Processing will be conducted off-site at a toll treatment plant that utilises
conventional CIL methods for gold extraction. Haulage costs reflect processing at a
plant 95km from Munda.
Metallurgical recovery factors of 88% for oxide and transitional material and 80% for
fresh material are utilised. These recoveries are based on recent test work and
exclude earlier testwork showing intervals of higher recovery in fresh rock. The
average recovery used is 83.3%.
Cut-off Grades
Break-even (or cut-off) grades are those grades at which ore can be processed
profitably. This was calculated as part of the evaluation of the optimal pit shells.
The costs and factors used to calculate the processed ore/waste cut-off grades
were:
•
•
•
•
Gold price
Royalties
Costs comprising of Ore/Waste Differential, Grade Control, Ore Haulage, Ore
Processing and Administration
Processing Recovery
At a $3,500 per ounce gold price, the break-even grades are 0.78g/t Au for oxide
and transitional material and 0.84g/t Au for fresh material.
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
10 DECEMBER 2024
Royalties
The Western Australian state gold royalty of 2.5% has been incorporated into the
optimisation process and subsequent optimum and pit design evaluations.
Estimation Methodology
The Probable Ore Reserves are reported within a detailed pit design and are
inclusive of mining dilution/ore loss, mining, haulage and processing costs,
metallurgical recoveries and the state royalty.
The operating costs used for the optimisation analysis and subsequent optimum shell
and pit mine design evaluations were either supplied by Auric or by Minecomp Pty
Ltd and are either based upon contemporary in-house knowledge or extracted
from Minecomp’s extensive operating cost database.
All inputs from mining operations, transportation, processing and sustaining capital
as well as contingencies have been scheduled on a monthly basis and evaluated
to generate a full life of mine cost model.
Tenure and Permitting Status
The Munda Starter Pit Ore Reserve is located within granted mining lease M15/87
with site access from the Coolgardie – Esperance Highway via an approved
miscellaneous licence, L15/414. Permit applications for water extraction and for
Native Vegetation Clearing have been submitted. Other environmental permit
applications are still to be submitted. The Munda Starter Pit will overlap an existing
pit within a current mining lease and it is reasonable to assume that all approvals
required to mine will be received.
Infrastructure Requirements
The Munda Starter Pit Ore Reserves plan will require installation of site infrastructure.
There is suitable terrain within the granted mining lease and miscellaneous licence
for the installation of all required infrastructure including a haul road extension,
waste dump, ROM pads, site office, workshop and site roads. Water will be available
for dust suppression from the historic 132 North pit under the terms of an agreement
with WIN Metals Ltd 2.
Capital and Start-up Cost Information
Capital and start-up cost requirements for the mining of the Munda Starter Pit
include, but may not be limited to mobilisation, site office and ablutions,
maintenance workshop and laydown area, establishment of services, clearing and
2 (ASX:AWJ) 23 July 2024. Munda Gold Project. Auric Buys Specific Mineral Rights and related assets from WIN
Metals for $1.2M.
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
10 DECEMBER 2024
grubbing and stockpiling of topsoil, haul road extension (2.7km) and demobilisation.
These costs have been estimated at $650,000 and have been included in the
optimum shell and pit design evaluations.
Mining Schedule and Working Capital Requirements
To estimate the working capital requirements for the Munda Starter Pit, a mining
schedule and cash flow model were developed.
The mining schedule is represented in Figure 2 and cash flow analysis in Figure 3.
Cash-flow analysis of the proposed mining schedule indicates a maximum cash
draw-down of $4.86M. Incorporating a 35% contingency results in the working
capital required to fund the Munda Starter Pit being $6.5M.
Any delay to the treatment of ore via toll milling leads to a requirement for working
capital to fund all mining costs but for haulage and processing costs to be funded
from gold sales. In that scenario, the working capital required is $6.2M and with a
35% contingency, $8.3M.
Figure 2. Munda Starter Pit – Production Schedule Tonnages.
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
10 DECEMBER 2024
Figure 3. Munda Starter Pit – Monthly Cost/Cash-flow Analysis.
Sensitivity Analysis
Sensitivity of the Munda Starter Pit operating profit to changes in gold price, mining
costs, ore haulage costs, ore processing costs and total costs are represented
graphically in Figure 4.
Figure 4. Munda Starter Pit – Operating Profit Sensitivities.
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
10 DECEMBER 2024
The Munda Starter Pit operating profit is most sensitive to gold price, followed by
total costs.
COMPLIANCE STATEMENT
The Information in this Report that relates to Ore Reserves is based on information
compiled by Mr Gary McCrae, a Competent Person who is a Member of the
Australasian Institute of Mining and Metallurgy. Mr McCrae is a full-time employee
of Minecomp Pty Ltd. Mr McCrae has sufficient experience that is relevant to the
style of mineralisation and type of deposit under consideration and to the activity
being undertaken to qualify as a Competent Person as defined in the 2012 Edition
of the “Australasian Code for Reporting of Exploration Results, Mineral Resources
and Ore Reserves”. Mr McCrae consents to the inclusion in the report of the matters
based on his information in the form and context in which it appears.
FORWARD LOOKING STATEMENTS
This Announcement may contain forward-looking statements which are identified
by words such as ‘may’, ‘could’, ‘should’, ‘believes’, ‘estimates’, ‘targets’,
‘expecting’, or ‘intends’ and other similar words that involve risks and uncertainties.
These statements are based on an assessment of present economic and operating
conditions, and on a number of assumptions regarding future events and actions
that, as at the date of this Announcement, are considered reasonable. Such
forward-looking statements are not a guarantee of future performance and involve
known and unknown risks, uncertainties, assumptions, and other important factors,
many of which are beyond the control of the Company, the Directors, and the
management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking
statements contained in this Announcement will actually occur and investors are
cautioned not to place undue reliance on these forward-looking statements.
This announcement has been approved for release by the Board of Auric Mining Ltd.
Corporate Enquiries
Investor Relations
Mark English
Managing Director
Auric Mining Limited
Alex Cowie
Director
NWR Communications
T +61 409 372 775
E menglish@auricmining.com.au
T +61 412 952 610
E alexc@nwrcommunications.com.au
Auric Mining Limited
ACN 635 470 843
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
Follow our
communications
Click here to
subscribe to our
updates
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
10 DECEMBER 2024
Appendix A Munda JORC Table 1 checklist
Section 4 Estimation and Reporting of Ore Reserves – Munda
Criteria
JORC Code explanation
Commentary
Mineral
Resource
estimate for
conversion to
Ore Reserves
• Description of the
Mineral Resource
estimate used as a basis
for the conversion to an
Ore Reserve.
• Clear statement as to
whether the Mineral
Resources are reported
additional to, or inclusive
of, the Ore Reserves.
Site visits
• Comment on any site
visits undertaken by the
Competent Person and
the outcome of those
visits.
• If no site visits have been
undertaken indicate why
this is the case.
• The type and level of
study undertaken to
enable Mineral
Resources to be
converted to Ore
Reserves.
• The Code requires that a
study to at least PreFeasibility Study level has
been undertaken to
convert Mineral
Resources to Ore
Reserves. Such studies
will have been carried
out and will have
determined a mine plan
that is technically
achievable and
economically viable,
and that material
Modifying Factors have
been considered.
• The basis of the cut-off
grade(s) or quality
parameters applied.
• A JORC 2012 compliant Mineral Resource
estimate was completed by Mr Jonathon
Abbott a Competent Person of Matrix
Resource Consultants Pty Ltd in November
2024. The mineral resource estimate model
is a recoverable resource model which is
inclusive of Gold only. This Mineral
Resource estimate is the basis for Auric’s
Munda Updated Mineral Resources
announcement dated 10 December 2024
• The Mineral Resources are reported
inclusive of the Ore Reserve.
• No site visits have been undertaken by the
Competent Person (Gary McCrae).
• Site visits would not materially affect the
determination of the Ore Reserve
Study status
Cut-off
parameters
Auric Mining Limited
ACN 635 470 843
• The Ore Reserve is based upon the
November 2024 pre-feasibility study.
• As part of the pre-feasibility study a mine
plan which is technically achievable and
economically
viable
has
been
developed.
• Material Modifying Factors have been
considered as part of the mine plan.
• The cut-off grade is calculated as part of
the mine optimisation analysis. For Ore
Reserve calculations the cut-off grade
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
Mining factors
or
assumptions
Auric Mining Limited
ACN 635 470 843
• The method and
assumptions used as
reported in the PreFeasibility or Feasibility
Study to convert the
Mineral Resource to an
Ore Reserve (i.e. either
by application of
appropriate factors by
optimisation or by
preliminary or detailed
design).
• The choice, nature and
appropriateness of the
selected mining
method(s) and other
mining parameters
including associated
design issues such as prestrip, access, etc.
• The assumptions made
regarding geotechnical
parameters (e.g. pit
slopes, stope sizes, etc),
grade control and preproduction drilling.
• The major assumptions
made and Mineral
Resource model used for
pit and stope
optimisation (if
appropriate).
• The mining dilution
factors used.
• The mining recovery
factors used.
• Any minimum mining
widths used.
• The manner in which
Inferred Mineral
Resources are utilised in
mining studies and the
•
•
•
•
•
•
•
•
•
•
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
10 DECEMBER 2024
was 0.78g/t gold for oxide and transitional
and 0.84g/t for fresh. Revenue based
assumptions considered in the cut-off
grade calculations included an assumed
gold price of A$3,500/oz, the WA State
Government gold royalty of 2.5% and
processing recoveries of 88% for oxide and
transitional ore and 82% for fresh.
The Mineral Resource was a recoverable
resource model. As such, no additional
mining dilution or mining recovery factors
were incorporated to produce the Ore
Reserve estimate.
A detailed mine design has been
completed.
The ore zone geometries coupled with the
regolith profiles and overall pit depth (<65
metres)
indicate
that
mining
by
conventional drill and blast and load and
haul open pit mining methods is most
suitable.
The mining fleet was assumed to be owner
operated and comprised of articulated
trucks and matching excavator and
ancillary equipment.
The geotechnical parameters used for
optimisation and pit design were based
upon those recommended by Peter
O’Bryan and Associates in the Munda,
Preliminary Geotechnical Assessment
report dated August 2024.
The Ore Reserve has been determined
using the November 2024 mineral resource
estimate generated by Mr Jonathan
Abbott of Matrix Resource Consultants Pty
Ltd.
The mineral resource estimate model is a
recoverable resource model and as such
is inclusive of mining dilution and mining
recovery.
No minimum mining widths were utilised.
Inferred Resources were assumed to be
waste material throughout the course of
the study and in the subsequent Ore
Reserve calculation.
The infrastructure required for the Munda
open pit operations has been accounted
for and has been included in the work
which formed the basis for the Ore Reserve
estimate. Planned infrastructure includes:
• Site offices and ablutions.
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
sensitivity of the outcome
to their inclusion.
• The infrastructure
requirements of the
selected mining
methods.
Metallurgical
factors or
assumptions
• The metallurgical process
proposed and the
appropriateness of that
process to the style of
mineralisation.
• Whether the
metallurgical process is
well-tested technology
or novel in nature.
• The nature, amount and
representativeness of
metallurgical test work
undertaken, the nature
of the metallurgical
domaining applied and
the corresponding
metallurgical recovery
factors applied.
• Any assumptions or
allowances made for
deleterious elements.
• The existence of any bulk
sample or pilot scale test
work and the degree to
which such samples are
considered
representative of the
orebody as a whole.
• For minerals that are
defined by a
specification, has the ore
reserve estimation been
based on the
appropriate mineralogy
to meet the
specifications?
Environmental • The status of studies of
potential environmental
impacts of the mining
and processing
operation. Details of
Auric Mining Limited
ACN 635 470 843
10 DECEMBER 2024
Maintenance Workshop.
Services including, electrical power
(supply, transmission, and distribution),
water and compressed air.
• Access/Haul Road (2.7km)
• ROM Pad
Processing will be conducted off-site at a
nearby Third Party owned and operated
ore processing
facility under a toll
treatment arrangement.
The ore processing facility utilizes
conventional CIP methods.
CIP is a well-tested existing metallurgical
technology.
The metallurgical recoveries used for the
estimation of the Ore Reserve are based
upon
testwork
completed
on
representative samples of Munda ore by
Mr Lee Richardson of Upside Metallurgy.
Based upon the findings of the
metallurgical testwork gold recovery of
88% for oxide and transitional ore and 80%
for fresh ore have been utilised for this
study.
It is expected that no deleterious elements
will be encountered.
Non-available
Not applicable, gold only.
•
•
•
•
•
•
•
•
•
•
• Environmental permitting is still to be
submitted to the Western Australian DMIRS
and DWER. Given that Munda is on
granted mining tenements adjacent to a
historical open pit operation it is
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
Infrastructure
Costs
Auric Mining Limited
ACN 635 470 843
waste rock
characterisation and the
consideration of
potential sites, status of
design options
considered and, where
applicable, the status of
approvals for process
residue storage and
waste dumps should be
reported.
• The existence of
appropriate
infrastructure: availability
of land for plant
development, power,
water, transportation
(particularly for bulk
commodities), labour,
accommodation; or the
ease with which the
infrastructure can be
provided or accessed.
• The derivation of, or
assumptions made,
regarding projected
capital costs in the study.
• The methodology used
to estimate operating
costs.
10 DECEMBER 2024
reasonable to assume that all approvals
will be received.
• Waste rock is typically non-acid forming.
• Waste material will be stored in a
conventional above surface waste dump.
• Ore processing and tailings storage will
occur off-site at Third Party owned and
operated facility under a toll treatment
arrangement.
• The Ore Reserve mine plan will require
installation
of
infrastructure.
The
infrastructure requirements include:• Site offices and ablutions.
• Maintenance Workshop.
• Services including electrical power
(supply, transmission, and distribution),
water and compressed air.
• Haul Road (2.7km)
• The tenement encompassing the Munda
project area is a granted mining lease with
sufficient and suitable terrain for the supply
and
installation
of
all
required
infrastructure. As such the Competent
Person sees no reason the infrastructure
could not be installed at the site.
• Sufficient water will be available for
operations through the course of
dewatering a nearby abandoned open
pit.
• All processing infrastructure including the
tailings storage facility is in place at the
Third Party owned and operated
processing facility.
• Site access is via the CoolgardieEsperance Highway, a gazetted road, an
existing, well-maintained, site access road
and an additional 2.7km of to be
constructed.
• Labour will be sourced from Kalgoorlie,
Coolgardie or Kambalda and where
applicable housed and messed in
Kambalda.
• Capital costs are
derived from
contemporary in-house knowledge and
experience in the establishment of similar
mining operations.
• Operating costs have been based upon
supplier and contract quotes as well as
contemporary in-house knowledge and
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
Revenue
factors
Market
assessment
Auric Mining Limited
ACN 635 470 843
• Allowances made for the
content of deleterious
elements.
• The derivation of
assumptions made of
metal or commodity
price (s), for the principal
minerals and coproducts.
• The source of exchange
rates used in the study.
• Derivation of
transportation charges.
• The basis for forecasting
or source of treatment
and refining charges,
penalties for failure to
meet specification, etc.
• The allowances made for
royalties payable, both
Government and
private.
• The derivation of, or
assumptions made
regarding revenue
factors including head
grade, metal or
commodity price(s)
exchange rates,
transportation and
treatment charges,
penalties, net smelter
returns, etc
• The derivation of
assumptions made of
metal or commodity
price(s), for the principal
metals, minerals and coproducts.
• The demand, supply and
stock situation for the
particular commodity,
consumption trends and
factors likely to affect
supply and demand into
the future.
• A customer and
competitor analysis
along with the
identification of likely
•
•
•
•
•
•
•
10 DECEMBER 2024
experience of those for similar mining
operations.
None present
An assumed gold price of A$3,500/oz has
been adopted for the financial modelling
as per Auric corporate guidance.
Single commodity pricing for gold only.
Cost models use Australian dollars.
All transportation charges are based upon
contemporary in-house knowledge and
were supplied by Auric. .
All treatment charges are based upon
contemporary in-house knowledge and
were supplied by Auric.
Allowances have been made for the 2.5%
Western Australian State Gold Royalty. No
other 3rd Party Royalties are applicable.
• Using a long-term gold price of A$3,500/oz
as per Auric corporate guidance.
• Single commodity pricing for gold only,
using a long-term gold price of A$3,500/oz
as per Auric corporate guidance.
• Perth
Mint
gold
price
on
the
22ndNovember 2024 was A$4,140/oz.
• Gold doré will be sold at spot price to the
Perth Mint as it is produced.
• The market window is unlikely to change.
• The price is likely to go up, down or remain
the same.
• Not an industrial mineral.
Level 1, 1 Tully Road, East Perth WA 6004
PO Box 1057, Joondalup DC WA 6919
info@auricmining.com.au
08 9548 9997
auricmining.com.au
ASX: AWJ
ANNOUNCEMENT TO THE AUSTRALIAN STOCK EXCHANGE
•
•
Economic
•
•
Social
Other
Auric Mining Limited
ACN 635 470 843
market windows for the
product.
Price and volume
forecasts and the basis
for these forecasts.
For industrial minerals the
customer specification,
testing and acceptance
requirements prior to a
supply contract.
The inputs to the
economic analysis to
produce the net present
value (NPV) in the study,
the source and
confidence of these
economic inputs
including estimated
inflation, discount rate,
etc.
NPV ranges and
sensitivity to variations in
the significant
assumptions and inputs.
• The status of agreements
with key stakeholders
and matters leading to
social license to operate.
To the extent relevant, the
impact of the following
on the project and/or on
the estimation and
classification of the Ore
Reserves:
• Any identified material
naturally occurring risks.
• The status of material
legal agreements and
marketing arrangements.
• The status of
governmental
agreements and
10 DECEMBER 2024
• The Ore Reserve is based upon a financial
model that has been prepared to a prefeasibility study level of accuracy. All
Inputs from mining operations, processing,
transportation and sustaining capital as
well as contingencies have been
scheduled and evaluated to generate a
full life of mine cost model.
• Economic inputs were supplied by Auric
based upon supplier and contract quotes
as well as contemporary in-house
knowledge and experience of those for
similar mining operations.
• No discount rate has been applied.
• The NPV of the project is positive at the
cost parameters and assumed gold price.
• Sensitivity analyses to gold price, mining
costs, ore haulage costs and ore
processing costs have been completed.
• The Ore Reserve is still economically viable
with a downward commodity price
movement of approximately 25%
• Consultation, where applicable with key
stakeholders
including
traditional
landowner
claimants
has
been
undertaken.
• A risk review has been completed. No
material risks are identified.
• None known with Auric intending to sell
gold produced from the operation at spot
price.
• The Ore Reserve and associated gold
ounces are contained within granted
mining tenements.
• A Project Management Plan and Mining
Proposal are yet to be submitted to
Western Australian DEMIRS. Given that
Munda is on a granted mining tenements
adjacent to historical op