Quarterly Activities Report
Released
Released
Announcement PDF
Auric Mining Limited
ABN 29 635 470 843 | ASX: AWJ
QUARTERLY
ACTIVITIES REPORT
30 SEPTEMBER 2026
Quarterly Activities Report September 2026 15 October 2026
1
HIGHLIGHTS
Integrated Scoping Study - Burbanks and Munda
• The Integrated Burbanks and Munda Scoping Study was released on 27 July 2026, outlining a single open pit at Munda
feeding a redesigned 600,000tpa CIL processing plant at Burbanks. At a base case gold price of A$5,750/oz, the study
estimates production of 141koz (recovered) over 56 months at an AISC of A$2,843/oz, generating EBITDA of
A$437M1
.
• Subsequent to the Integrated Scoping Study, the Company acquired a substantial package of fixed plant processing
infrastructure for the re-establishment of the Burbanks processing facility. At a cost of A$1.2 million, the acquisition
represents a significant discount to the estimated A$15–20 million replacement cost of equivalent new equipment.
Removal of this infrastructure package from NSW and transport to Burbanks will be completed by Interquip during
the December 2026 quarter, ready for construction in 2027.
• Construction of the Burbanks processing plant is expected to commence following receipt of approvals in early 2027.
First gold from Burbanks is targeted for early 2028.
Projects
• Four drilling programs were under way or completed at the Munda Gold Mine during the quarter, including resource
extension, grade control, geotechnical and sterilisation drilling. These programs support pit design and operational
readiness activities ahead of the planned recommencement of mining in late 2027.
• Broad-spaced RC drilling targeting extension of the Munda resource, west of the planned open pit, returned a large
number of mineralised zones, including 4m @ 10.49g/t Au from 46m (AMRC072), supporting the potential to grow
the Mineral Resource along strike beyond the current pit design.
• Initial results from close-spaced grade control drilling targeting the upper 30m of the planned pit show a similar grade
distribution to the Starter Pit and include: 15m @ 5.56g/t Au from 6m, 4m @ 19.34g/t Au from 9m, 9m @ 7.82g/t
Au from 17m, 14m @ 3.92g/t Au from 6m and 10m @ 4.66g/t Au from 13m.
• Geotechnical diamond drilling was completed, providing the final component needed to confirm the final pit design
and define Ore Reserves, which are expected to be announced in October 2026.
• Other operational readiness activities continued during the quarter, including progression of statutory approvals,
detailed plant engineering and planning for the Munda camp expansion.
Union Jack Acquisition
• The Company executed two binding agreements to acquire the Union Jack Project, 5km east of Coolgardie and 15km
from Burbanks. Settlement and completion occurred on 6 October 2026. Union Jack has an Inferred Mineral Resource
of 3.12Mt @ 1.02g/t Au for 102,000oz, which increases Auric’s total Mineral Resource inventory by 51% to 7.5Mt @
1.25g/t Au for 301,000oz. Initial consideration for the Union Jack Project totals A$6.6 million cash and A$3.0 million
in shares, to be issued at A$0.24/share, subject to shareholder approval.
Exploration
• Regional exploration activity commenced during the quarter including aircore programs in the Higginsville and
Widgiemooltha project areas with additional programs planned in the Higginsville, Spargoville and Lindsays project
areas.
Corporate
• The Company reported a net profit before tax of A$28.0 million and net profit after tax of A$19.3 million for the half-
year ended 30 June 2026, on revenue of A$44.8 million.
• During the quarter 800,000 unquoted options were exercised at A$0.15 each, bringing total issued capital at 30
September 2026 to 187,893,602 shares.
• Cash and cash equivalents at 30 September 2026 were A$33.05 million, after spending A$1.2 million for plant &
equipment for Burbanks and A$2.7 million on exploration and drilling costs during the quarter.
• The Company has no debt other than vehicle financing and is unhedged.
1 Refer ASX announcement 27/7/2026
Quarterly Activities Report September 2026 15 October 2026
2
MANAGING DIRECTOR, MARK ENGLISH, SAID:
“The September Quarter has been one of rapid expansion for Auric. Having released our Integrated Scoping Study, we
moved immediately into delivery, with four drilling programs running concurrently at Munda, providing encouraging
results including the potential to grow the Resource along strike beyond the current pit design, and strong near-surface
mineralisation within the planned open pit.
“We have secured a substantial package of fixed plant infrastructure for the Burbanks rebuild at a significant discount to
replacement cost, locking in both the capital estimates and development timeline used in our study.
“We acquired Union Jack, which dovetails perfectly with our strategy of acquiring near-term gold production assets within
trucking distance of the Burbanks Mill.
“With ongoing drilling, Ore Reserve work advancing, and detailed design along with processing infrastructure purchases,
we are steadily de-risking the next stage of development ahead of the planned rebuild of the Burbanks Processing Plant
and recommencement of mining in 2027.”
QUARTERLY ACTIVITIES REPORT
Auric Mining Limited (ASX: AWJ) (“Auric” or “the Company”) is pleased to report on activities during the quarter ended
30 September 2026.
Integrated Scoping Study
On 27 July 2026 the Company released the outcomes of the Integrated Burbanks and Munda Scoping Study which
support the re-establishment of the Burbanks processing facility and the restart of mining at the Munda gold deposit.
Re-establishment of Burbanks provides Auric with strategic control of critical processing infrastructure in a region with
limited available gold treatment capacity, positioning the Company to unlock value from Munda while creating a platform
to capture future organic and inorganic opportunities. The capital estimate for the Burbanks re-establishment has been
completed to PFS-level accuracy while the overall integrated study is a Scoping Study, reflecting the additional technical,
permitting and development work required at Munda.
The study considers a large single open pit at Munda providing 2,769,177t of mineralised material at 1.75g/t Au for
155,844 ounces, of which 93.1% is in the Indicated Mineral Resource category with the balance Inferred, plus existing
Starter Pit stockpiles of 76kt @ 0.81g/t Au for 1,980 ounces. Mining is planned over 32 months using conventional,
owner-operated equipment at an overall strip ratio of 11:1. Burbanks has been redesigned to target a nominal
600,000tpa throughput rate, processing all available material from Munda over 56 months for recovered production of
141,254oz (89.5% recovery), with annual gold production of between 25,000 and 40,000 ounces over the first four years
and lower-grade stockpiles processed in year five. The plant is designed to be scalable to 1.2Mtpa through a series of
simple upgrades. Key physical and financial outcomes at a range of gold prices are summarised in Table 1.
Table 1. Integrated Scoping Study – physical and financial summary
Metric Unit A$5,250/oz A$5,750/oz (Base) A$6,250/oz
Mineralised material mined Mt 2.77 2.77 2.77
Grade mined g/t Au 1.75 1.75 1.75
Ounces mined koz 155 155 155
ROM processed Mt 2.84 2.84 2.84
Recovery % 89.5 89.5 89.5
Gold produced koz 141 141 141
Pre-production capital A$M (138) (138) (138)
Peak funding requirement A$M (147) (145) (145)
Payback years 2.5 2.3 2.1
Total gross revenue A$M 742 812 883
AISC A$/oz 2,830 2,843 2,857
EBITDA A$M 368 437 506
Pre-production capital comprises the Burbanks re-instatement (A$94.3M, PFS-level ±15%, estimated by Interquip Pty Ltd as an EPCM plant
build), owner’s costs (A$35.8M, ±25%) and the Munda open pit establishment (A$7.5M, ±25%). Working capital of A$17.4M is partially offset
by approximately A$9.3M of gold revenue during commissioning. Average annualised EBITDA for the initial project is ~A$94M per annum.
Quarterly Activities Report September 2026 15 October 2026
3
Auric plans to execute the project through a staged program of permitting, detailed engineering, procurement,
construction, mining and commissioning. The Company is working through all required approvals which are expected in
early 2027 ahead of the commencement of construction at Burbanks with first gold targeted for early 2028. Mining is
forecast to begin ahead of mill commissioning to establish processing stocks for ramp-up.
Munda Gold Mine
Major Drilling Programs at Munda
The Company commenced multiple drilling campaigns during the quarter, including broad-spaced RC drilling targeting
potential extensions of the Munda gold deposit, grade control drilling, geotechnical diamond drilling to define pit wall
parameters and RC sterilisation drilling to confirm the site of the Waste Rock Landform (Figures 1 and 3).
Western extension RC drilling. The Munda Mineral Resource remains open along strike and at depth, with initial drilling
targeting a western extension to the orebody, along strike from previous results that include:
• 13m @ 14.62g/t Au from 60m (AMRC012),
• 5m @ 3.46g/t Au from 87m (AMRC005), and
• 4m @ 3.34g/t Au from 46m (AMRC050).
The western extension RC program is being undertaken by Drill Safe Services and comprises 135 holes for approximately
12,900m, testing for gold mineralisation to a depth of 120m within the mafic volcanics which host the bulk of the Munda
Resource.
Initial results include an intercept of 4m @ 10.49g/t Au from 46m (AMRC072) together with a large number of significant
intercepts at a 0.5g/t cut-off. The pattern of results is similar to the Starter Pit area and the distribution of assays in the
northern-most holes of the drill traverses vectors further drilling toward the ultramafic contact (Figure 2), where the
next phase of extension drilling targeting that area will commence shortly. RC drilling will also commence below the
deepest section of the designed pit over the coming months, targeting extension and/or future underground potential.
RC grade control drilling. The first stage of grade control drilling at 5m x 5m spacing is being undertaken by Kalgoorlie-
based Total Drilling Services. Approximately 90,000m of RC grade control drilling is planned over 15 months as the grade
control rig progressively drills the as-modelled Mineral Resource panels from surface within the Stage 2 pit design. The
program will provide definition of ore blocks down to approximately 30m below surface and will ensure a smooth ramp-
up to full production in concert with commissioning of the 600ktpa Burbanks processing plant. Mining of the Starter Pit
demonstrated that localised high grades have a considerable influence on the overall gold inventory, and the Stage 2
grade control drilling continues to demonstrate the same style of mineralisation (Figure 1). Significant intercepts at a
0.5g/t Au cut-off include:
• 9m @ 7.82 g/t from 17m, including 1m @ 26.40 g/t,
• 10m @ 4.66 g/t from 13m,
• 15m @ 5.56 g/t from 6m, including 3m @ 19.30 g/t,
• 5m @ 8.73 g/t from 12m, including 1m @ 25.80 g/t,
• 4m @ 19.34 g/t from 9m, including 2m @ 38.10 g/t,
• 3m @ 11.61 g/t from 19m, including 1m @ 33.2 g/t,
• 14m @ 3.92 g/t from 6m, including 1m @ 35.20 g/t, and
• 9m @ 5.00 g/t from 3m.
Quarterly Activities Report September 2026 15 October 2026
4
Figure 1. Munda – RC extension and grade control drill holes (red) with significant assays (0.5g/t cut-off, >30 gram-metres).
Figure 2. Munda 2026 western extension RC drill holes (red) and significant assays at a 0.5g/t Au cut-off.
Quarterly Activities Report September 2026 15 October 2026
5
Geotechnical diamond drilling. Four diamond drill holes were completed by Westralian Diamond Drillers for a total of
580m. The holes were drilled to determine geotechnical parameters for the pit walls and were logged and sampled by
Auric personnel under the supervision of geotechnical consultants Peter O’Bryan and Associates. The geotechnical
parameters provide the final component needed to confirm or refine the pit design, which in turn will allow the definition
of Ore Reserves. The Company expects to publish the Ore Reserve during October 2026, after optimisation and pit design
work has been completed.
Sterilisation drilling. Sterilisation drilling of the proposed waste dump location (Figure 3) has commenced, with 29 RC
drill holes completed so far for 1,475m. No assays have been received to date and the program is ongoing.
Mine Planning and Permitting
Preparation of the Mine Development and Closure Plan required for the next stage of mining is well advanced as are
plans to expand the mine camp. Mining at Munda is on track to recommence in late 2027.
Figure 3. Munda Gold Project – proposed Stage 2 site layout.
Quarterly Activities Report September 2026 15 October 2026
6
Burbanks Gold Processing Facility
The Burbanks Gold Processing Facility is located approximately 9 kilometres south of Coolgardie and is central to Auric's
strategy of becoming a fully integrated gold producer, providing an in-house processing solution for ore from Munda,
Union Jack, and potentially Lindsay’s and other nearby projects.
Processing Infrastructure Acquired
In September the Company announced the acquisition of a significant package of processing infrastructure comprising
key fixed plant equipment for re-establishment at Burbanks, purchased for A$1.2 million. The second-hand plant is in
excellent condition and is located at a closed mine site in New South Wales. The front-end fixed plant infrastructure
supports the initial 600ktpa Burbanks CIL plant design and provides a platform for future expansion to 1.2Mtpa. It
includes a complete three-stage crushing circuit; a fine ore bin and conveyors, material handling equipment and
enclosing shed, a milling structure and associated infrastructure, all associated spare parts and consumables including
two complete spare cone crushers and one complete spare jaw crusher.
Auric identified the infrastructure during preparation of the Integrated Scoping Study and incorporated the use of
comparable second-hand equipment into the study capital estimate. Completion of the acquisition secures those capital
and schedule benefits and maintains the study development timeline for re-establishment of the processing plant in the
March 2028 quarter. On an all-in basis, including the cost to relocate the equipment, the acquisition is estimated to
deliver a significant cost saving relative to purchasing equivalent new equipment, estimated at A$15–20 million. The
included spare equipment, parts and consumables are expected to reduce execution risk, future capital and operating
expenditure and the time needed to recommission the facility.
Interquip has been engaged to remove and relocate the infrastructure in the December 2026 quarter, with all equipment
expected to be on site at Burbanks ready to begin installation in the March 2027 quarter.
Figure 4. The acquired crushing and processing infrastructure, including mill structure, conveyors and triple-deck screening circuit.
Quarterly Activities Report September 2026 15 October 2026
7
Union Jack Project
On 9 September 2026 the Company announced that it had executed binding agreements to purchase the Union Jack
Project. The Project is located 5km due east of Coolgardie, ~15km from the Burbanks processing plant. It comprises
granted mining lease M15/120 and prospecting licence P15/6183, covering 89 hectares (Figure 5).
Union Jack has an Inferred Mineral Resource estimate of 3.12Mt @ 1.02g/t Au for 102,000 ounces of gold (0.5g/t Au cut-
off, within a A$7,000/oz RPEEE pit optimisation), reported in accordance with JORC 2012. Using a 0.65g/t Au cut-off
within the same optimised pit shell, the Project contains 2.16Mt @ 1.22g/t Au for 85,000 ounces, highlighting the
potential for Union Jack to provide additional feed for Burbanks. Settlement and completion occurred on 6 October 2026.
The acquisition increases the Company’s global Mineral Resource inventory by 51% to 7.5Mt @ 1.25g/t Au for 301,000
ounces.
The gold mineralisation at Union Jack remains open both along strike and at depth and the Company considers the
Project to have strong resource growth potential. Previous drilling into the shallow deposit includes: 17m @ 4.57g/t Au
from 24m, 15m @ 4.22g/t Au from 62m, 5m @ 9.64g/t Au from 10m, 10m @ 4.72g/t Au from 19m, 17m @ 3.99g/t Au
from 13m and 5m @ 12.21g/t Au from 56m, while limited deeper drilling has returned 16m @ 4.34g/t Au from 184m
and 2m @ 6.54g/t Au from 200m, indicating potential for extension at depth and underground potential.
Auric will undertake additional drilling targeting operational readiness and open-pittable resource growth, with the
objective of adding additional Auric-owned ore to the operating life of the Burbanks processing plant.
Key terms of the acquisition of M15/120 include an initial consideration of $6,500,000 and the issue of 12,500,000 fully
paid ordinary shares at A$0.24 per share (A$3,000,000), to be issued subject to shareholder approval, and milestone
payments of up to $7,000,000 on the definition of additional gold resources up to 200,000 ounces. Auric has committed
to spend $2,000,000 on drilling over the first 5 years and will pay the vendor a gross royalty of 1.0% on all gold produced
and sold from M15/120. The Company has separately paid A$100,000 to an unrelated third party as consideration for
the acquisition of Prospecting Licence P15/6183.
Figure 5. Union Jack historic workings, drill holes and resource pit outline relative to tenure.
Quarterly Activities Report September 2026 15 October 2026
8
Lindsay’s Gold Project
The Lindsay’s Gold Project, located approximately 65 kilometres northeast of Kalgoorlie, forms part of Auric's strategy
to develop a pipeline of near-infrastructure gold projects. Auric executed a Tenement Sale Agreement (TSA) with Top
Global Mining (TGM) in November 2025 to acquire the tenements making up the project. Prior to transfer of the
tenements, applications for forfeiture were made against some of the leases and the transfer process has been halted
until after the Wardens Court has handed down the decisions. The Wardens' Court proceedings remained ongoing during
the September 2026 Quarter. Auric has completed and finalised the acquisition of 4 tenements from TGM.
Exploration
Drilling
Regional exploration activity during the quarter included aircore programs in the Higginsville and Widgiemooltha project
areas with no substantial results returned to date but many results pending. Additional programs are planned in the
Higginsville, Spargoville and Lindsay’s project areas and at Union Jack with a focus on the latter.
Safety
There were no lost time injuries (LTI), medically treated injuries (MTI) or alternate duty injuries (ADI) recorded during
the quarter.
Tenements
The schedule of mining tenements held by Auric Mining Limited and its subsidiaries as at 30 September 2026 is set out
at the end of this report. One tenement was granted and applications were lodged for three tenements during the
September 2026 Quarter. Auric holds interests across the Widgiemooltha (including Munda and Loded Dog), Jeffreys
Find, Spargoville, Chalice West, Burbanks, Coolgardie (including Union Jack) and Lindsay's Projects.
Table 2. Tenement granted during September 2026 Quarter
Tenement Project Mineral Rights
E15/2151 Widgie Gold 100% All Minerals
Table 3. Tenement applications during September 2026 Quarter
Tenement Project Mineral Rights
L15/541 Burbanks Infrastructure
L15/542 Burbanks Infrastructure
E16/690 Coolgardie 100% All Minerals
The schedule of mining tenements held by Auric Mining Limited and its subsidiaries as at 30 September 2026 is set out
at the end of this report. The Union Jack tenement (M15/120) (Table 4) were subject to completion at the 30 September
2026. Completion occurred on 6 October 2026.
Table 4. Tenements acquired during September 2026 Quarter
Tenement Project Mineral Rights
M15/120 Union Jack 100% All Minerals (completed on 6 October 2026)
P15/6183 Union Jack 100% All Minerals
Auric also continued to engage with the Marlinyu Ghoorlie native title claimant group in respect to a claim wide
agreement for future operations.
Farm-in or Farm-out Agreements
The Company is not party to any Farm-in or Farm-out agreements.
Quarterly Activities Report September 2026 15 October 2026
9
Mining Exploration, Development and Production Activities
In accordance with ASX Listing Rule 5.3.1, the Company advises that approximately $2.71 million was incurred on
exploration and evaluation activities during the quarter, predominantly on the drilling programs at Munda and regional
aircore drilling. A summary of the exploration activities undertaken in each project area is provided in the relevant
sections of this report. In accordance with ASX Listing Rule 5.3.2, the Company advises that no mining development or
production activities were conducted during the quarter, other than the acquisition of the infrastructure for the Burbanks
processing facility as stated in this report.
CORPORATE / FINANCIAL
Board and Management
There were no changes to the Board during the quarter.
Half-Year Financial Report
On 2 September 2026 the Company released its Half-Year Financial Report for the half-year ended 30 June 2026. The
Company reported record revenue and profit, driven by gold production from the Munda Starter Pit, with 6,168oz
produced during the half-year bringing total Starter Pit production to 8,886oz at an AISC of A$2,857/oz. Key results are
summarised in Table 5.
Table 5. Half-year ended 30 June 2026 – key results
Item H1 2026 H1 2025
Total revenue A$44.8M A$0.34M
Net operating cash flow A$33.8M –
Net profit/(loss) before tax A$28.0M (A$1.35M)
Net profit/(loss) after tax A$19.3M (A$0.18M)
Earnings per share 10.29 cents (0.09) cents
Cash at 30 June 2026 A$38.0M –
Total assets at 30 June 2026 A$62M –
Cash
At 30 September 2026 Auric Mining held cash and cash equivalents of $33.05M. The Company’s main cash expenditure
during the quarter related to drilling & exploration ($2.71M) as well as buying plant & equipment for the Burbanks plant
($1.20M).
The Company has no debt other than vehicle financing and is unhedged.
Securities on Issue
During the quarter the Company issued 800,000 fully paid ordinary shares on the exercise of unquoted options
exercisable at $0.15 each (300,000 shares issued on 14 August 2026 and 500,000 shares issued on 15 September 2026).
At 30 September 2026 Auric Mining had 187,893,602 fully paid ordinary shares on issue, 18,323,748 options with various
conversion terms and dates, and 33,500,000 performance rights with various hurdles.
Related Party Payments
The Company paid salaries, superannuation, annual leave and other employment entitlements to full time employee
Directors and related parties of the Company of approximately $393,866 during the quarter. The Company also paid
$16,665 to Director-related parties of the Company. These costs are included in administration costs and working capital
except when technical staff are working in the field, in which case those direct costs are allocated to the relevant
tenements and projects and are included in the 30 September 2026 Appendix 5B.
Quarterly Activities Report September 2026 15 October 2026
10
ASX COMPLIANCE
Compliance Statement
The information in this report that relates to exploration results, Mineral Resources and production targets is extracted
from the Company's following ASX announcements, which are available to view on the Company's website,
www.auricmining.com.au:
Date Details
3 Jul 2026 Appendices 3G – Correction and Clarification; Change of Director’s Interest Notices
27 Jul 2026 Integrated Study Supports the Development of Burbanks and Munda
28 Jul 2026 Major Drilling Programs Commenced at Munda
29 Jul 2026 June 2026 Quarterly Activities Report and Appendix 5B
5 Aug 2026 Change of Director’s Interest Notice – Mark English
17 Aug 2026 Application for quotation of securities and Cleansing Statement
2 Sep 2026 Half-Year Results – $28 Million Profit Before Tax
7 Sep 2026 Trading Halt
9 Sep 2026 Union Jack Project – Strategic Acquisition and Resource Upgrade
9 Sep 2026 Proposed issue of securities and Update – Proposed issue of securities
16 Sep 2026 Significant Processing Infrastructure Acquired for Burbanks
16 Sep 2026 Application for quotation of securities and Cleansing Statement
24 Sep 2026 Strong Drilling Results Ahead of Larger Munda Development
ASX Announcements referred to from previous quarters:
Date Details
10 Dec 2024 Munda Gold Deposit Starter Pit Ore Reserve
1 Dec 2025 Munda Gold Mine Campaign One Results
30 Apr 2026 2025 Annual Report (Jeffreys Find Mineral Resource)
25 May 2026 Munda Gold Deposit Mineral Resource Increased by 32%
5 Jun 2026 Clarification Announcement: Munda Gold Deposit Mineral Resource Increased by 32%
The Company confirms that it is not aware of any new information or data that materially affects the information
included in the original market announcements referred to above and, in relation to the Munda, Jeffreys Find and Union
Jack Mineral Resources, that all material assumptions and technical parameters underpinning the estimates continue to
apply and have not materially changed. The Company confirms that all material assumptions underpinning the
Production Targets, or the forecast financial information derived from the Production Targets, included in the original
ASX announcement dated 27 July 2026 continue to apply and have not materially changed. The Company further
confirms that the form and context in which the Competent Persons' findings are presented have not been materially
modified from those original announcements.
Forward Looking Statements
This Announcement contains forward-looking statements which are identified by words such as 'may', 'could', 'should',
'believes', 'estimates', 'targets', 'expected', or 'intends' and other similar words that involve risks and uncertainties. These
statements are based on an assessment of present economic and operating conditions, and on a number of assumptions
regarding future events and actions that, as at the date of this Announcement, are considered reasonable. Such forward-
looking statements are not a guarantee of future performance and involve known and unknown risks, uncertainties,
assumptions and other important factors, many of which are beyond the control of the Company, the Directors and the
management. The Directors cannot and do not give any assurance that the results, performance or achievements
expressed or implied by the forward-looking statements contained in this Announcement will actually occur and
investors are cautioned not to place undue reliance on these forward-looking statements.
Quarterly Activities Report September 2026 15 October 2026
11
Figure 6. Auric’s projects in the Widgiemooltha-Norseman area.
Quarterly Activities Report September 2026 15 October 2026
12
Auric Mining Ltd
Auric Mining Ltd was established to explore for and develop gold and other mineral deposits in the Widgiemooltha–
Norseman area of Western Australia. Auric has tenements covering 616km². Auric holds the rights to gold on all
tenements, including those held in the name of Mt Edwards Critical Metals Pty Ltd. At Munda it holds all mineral rights
except lithium. For all other tenements, excluding those held in the name of Mt Edwards Critical Metals Pty Ltd, Auric
holds 100% of all mineral rights.
The tenements are separated into seven projects:
The Widgiemooltha Gold Project including the Munda Gold Mine and Loded Dog Project
Located near the town of Widgiemooltha, the Widgiemooltha Gold Project combines 35 tenements including 5 granted
Mining Leases. All tenements are highly prospective for gold mineralisation. Auric has mined and completed two
successful toll-milling campaigns from a Starter Pit at Munda and is drilling to support an Ore Reserve estimate and final
pit design for a much larger Munda open pit.
The Jeffreys Find Gold Mine
The Jeffreys Find Gold Mine is located 50km northeast of Norseman and combines 3 tenements including 1 granted
Mining Lease. Open pit mining was completed via a joint venture with BML Ventures Pty Ltd, with all surplus cash
distributions concluded during the March 2026 Quarter. The mine is currently on care and maintenance but there are
existing resources at Jeffreys Find which may become attractive at higher gold prices.
The Spargoville Project
The Spargoville Project is located 30km north of Widgiemooltha and combines 11 tenements. It lies in similar
stratigraphy, proximal to the Wattle Dam Gold Mine, which produced 268,000oz gold at 10g/t from 2006–13, one of
Australia's highest-grade mines at that time.
The Chalice West Project
Located 50km southwest of Widgiemooltha, the Chalice West Project combines 4 tenements and covers 245km²,
including geology mirroring the Chalice Gold Mine, which produced almost 700,000 ounces of gold. The project is also
prospective for Rare Earth Elements (REE) and Ni-Cu and Pt-Pd deposits.
The Burbanks Gold Processing Facility
The Burbanks Gold Processing Facility is located 9km south of Coolgardie and combines 15 tenements including 3 granted
Mining Leases and 5 General Purpose leases. The plant is fully permitted with access to grid power, sealed road, and a
water licence. It provides Auric with an in-house processing solution for gold ore from Munda, Union Jack, Lindsay's and
other nearby projects, and is central to the Company's ambition to become a fully integrated gold producer.
The Lindsay's Gold Project
The Lindsay's Gold Project is located 65km northeast of Kalgoorlie and currently combines 6 tenements. Auric has the
right to purchase 3 further tenements subject to resolution of Warden’s Court proceedings by third parties against those
tenements.
The Coolgardie Project, including Union Jack
The Coolgardie Project comprises three tenements and includes Union Jack which is located 5km east of Coo