Correction to Mining at Jeffreys Find Announcement
Released
Released
Announcement PDF
AURIC MINING LIMITED (ACN 635 470 843)
LEVEL 1, 1 TULLY ROAD, EAST PERTH WA 6004
WWW.AURICMINING.COM.AU
ASX CODE: AWJ
11 July 2023
ASX Market Release
Correction to ASX Announcement
Mining at Jeffreys Find
Maiden Gold Pour Only Weeks Away
Auric Mining Limited (ASX: AWJ) (Auric or the Company) wishes to advise a correction to the
announcement entitled “Mining at Jeffreys Find – Maiden Gold Pour Only Weeks Away” which was
released to the ASX at 8.36am on 11 July 2023 (ASX Announcement).
The ASX Announcement inadvertency contained a typographical error by omitting the word “ore”
as highlighted within the attached corrected announcement.
Mark English
Managing Director
This announcement has been approved for release by the Board.
Further information contact:
Mark English |0409 372 775
menglish@auricmining.com.au
page | 1
Auric Mining Limited (ACN 635 470 843)
Level 1, 1 Tully Road, East Perth WA 6004
+61 8 6155 9046
info@auricmining.com.au
www.auricmining.com.au
ASX Announcement
auricmining
11 July 2023
ASX: AWJ | ACN 635 470 843
Mining at Jeffreys Find
Maiden Gold Pour Only Weeks Away
Highlights
•
77,500 tonnes of gold ore on the ROM Pad at Jeffreys Find Gold Mine,
Norseman as at 9 July 2023.
•
More than 12,500 tonnes of ore has been delivered to The Greenfields Mill,
Coolgardie.
•
Initial batch of 30,000 tonnes to be processed shortly.
•
First gold pour projected by end of July.
•
Auric still expecting substantial cashflow in September/October.
The Announcement
Auric Mining Limited (ASX: AWJ) (Auric or the Company) is pleased to announce
that as at 9 July 2023 approximately 90,000 tonnes of gold ore has been mined at
Jeffreys Find with 77,500 tonnes of gold ore on the ROM (Run Of Mine) pad at its
Jeffreys Find Gold Mine. Trucking to the Greenfields Mill in Coolgardie has
commenced with around 12,500 tonnes delivered.
Operations are proceeding according to plan with mining underway for more than
six weeks.
The first 12,500 tonnes of ore body have now been transported to Coolgardie. Once
around 20,000 tonnes have been delivered to Greenfields the mill will commence
processing the initial batch of approximately 30,000 tonnes.
Over the coming months BML Ventures Pty Ltd of Kalgoorlie, Auric’s mining joint
venture partner, will mine and haul in total between 100,000 tonnes and 180,000
tonnes of ore to complete the first stage of the project.
page | 1
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 11 July 2023
Auric Mining Limited (ACN 635 470 843)
“We now have a well-established, open pit at the mine site and mining is
proceeding according to plan. Widespread rain in the district over the past fortnight
has hampered haulage to the mill, but mining is continuing,” said Auric’s Managing
Director Mark English.
“With 12,500 tonnes of ore already transported to Coolgardie we are just a short time
away from our maiden gold pour. Once the first approximately 30,000 tonnes is
processed it will be clear how this project is going to unfold. I can say both parties
are well satisfied with the effort to date,” he said.
77,500 tonnes of gold ore are now sitting on the ROM pad at Jeffreys Find.
After completing the first phase of mining the partners will subtract all costs,
including a cash retention for the second stage, before splitting the surplus cash
proceeds on a 50:50 basis. This will provide Auric with a substantial cash boost,
expected in September/October 2023.
The total project life is short and final mining is expected to be completed by the
end of 2024. A robust gold price has now placed the project in a favourable position.
page | 2
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 11 July 2023
Auric Mining Limited (ACN 635 470 843)
Gold is thickest near the surface at the Jeffreys Find Gold Mine.
“Auric will use surplus cash generated from Jeffreys Find to continue development
of the Munda Gold Deposit at Widgiemooltha and continue with broader
exploration,” said Mr. English.
The initial pit takes shape at the Jeffreys Find Gold Mine.
page | 3
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
ASX Announcement 11 July 2023
Auric Mining Limited (ACN 635 470 843)
Forward Looking Statements
This Announcement contains forward-looking statements which are identified by
words such as ‘may’, ‘could’, ‘should’, ‘believes’, ‘estimates’, ‘targets’, ‘expected’,
or ‘intends’ and other similar words that involve risks and uncertainties. These
statements are based on an assessment of present economic and operating
conditions, and on a number of assumptions regarding future events and actions
that, as at the date of this Announcement, are considered reasonable. Such
forward-looking statements are not a guarantee of future performance and involve
known and unknown risks, uncertainties, assumptions and other important factors,
many of which are beyond the control of the Company, the Directors, and the
management. The Directors cannot and do not give any assurance that the results,
performance, or achievements expressed or implied by the forward-looking
statements contained in this announce will actually occur and investors are
cautioned not to place undue reliance on these forward-looking statements.
Mark English
Managing Director
This announcement has been approved for release by the Board.
Further information contact:
Mark English |0409 372 775
menglish@auricmining.com.au
page | 4
+61 8 6155 9046 | info@auricmining.com.au | Level 1, 1 Tully Road, East Perth, WA 6004 | www.auricmining.com.au
Share your feedback